Eureka AIR delivers breakthrough ideas for toughest innovation challenges, trusted by R&D personnel around the world.

Parallel operation and load switching control method of 10kV generator set

A generator set and control method technology, applied in the direction of electrical components, circuit devices, emergency power supply arrangements, etc., can solve the problems of inability to automatically cut off non-important loads, reduce the safety of back-end load operation, and low system load rate, etc., to achieve high efficiency Reliable fault handling capability, reducing the probability of operating errors, and improving the effect of load rate

Active Publication Date: 2014-04-30
HUAXIN CONSULTATING CO LTD +1
View PDF2 Cites 6 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] 1. The paralleling process is an overall action, that is, all the configured generator sets need to be successfully paralleled before they can be used as power output. The overall paralleling time is long and the operation safety of the back-end load is reduced.
[0005] 2. The simple parallel system does not have automatic load switching control after the parallel machine is completed
[0006] 3. When one or more generator sets in the parallel system fail, the parallel system cannot automatically remove non-important loads. When the remaining unit capacity cannot meet the load capacity, that is, when the parallel system is overloaded, the entire parallel system will disintegrate, and the downstream load will be powered off
[0007] 4. The parallel system cannot automatically judge and stop the operation of some redundant units according to the actual capacity of the subsequent load, resulting in a low system load rate and a waste of energy

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Parallel operation and load switching control method of 10kV generator set
  • Parallel operation and load switching control method of 10kV generator set
  • Parallel operation and load switching control method of 10kV generator set

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0042] like Figure 1-6 As shown, the parallel operation and load switching control method of 10kV generator sets described in this embodiment is set to have n roads of mains, respectively 1#, 2#, ... n#, n is an even number, then:

[0043] 1. If any line of mains power fails, the diesel engine will start parallel operation. If there is still one line of mains power within 10 minutes, the oil engine will automatically stop. If the other line of mains power fails within 10 minutes, the oil machine will be paralleled. Put into use, and set according to the importance of the load, put the load in order;

[0044] 2. When the two-way mains power fails at the same time, the oil generators will start in parallel. When there are 2 parallel machines, the load will be put into operation, and the load will be put into order according to the importance of the load;

[0045] 3. Load input and removal are related to the number of oil generators in parallel, ensuring that the input load capac...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention aims to overcome the defects in the prior art, and provides a parallel operation and load switching control method of a 10kV generator set. According to the method, automation and intelligentization of parallel operation and load switching control are achieved through reasonable and accurate setting of a logical relationship, and accordingly a parallel operation system of the generator set accords with security characteristics of a communication network. Parallel operation and load switching management is achieved through a PLC, and the method mainly comprises control of the parallel operation system and control of load switching. In application of set parallel operation and the load switching management, the PLC achieves related functions ultimately by means of control over various breakers through collection of analog quantity and the switching value via logic setting of a user.

Description

technical field [0001] The invention relates to a parallel control method for 10kV generating sets, in particular to a paralleling and load switching control method for 10kV generating sets of a communication distribution network. Background technique [0002] In the communication industry, the diesel generator set is used as a backup power supply. When the mains power fails, the generator set starts within a certain period of time to provide power. At present, a diesel generator set with a voltage level of 400V is generally used. The set has a self-starting function and automatically switches with the mains (transformer back end). In recent years, with the increase in the scale of communication equipment rooms and the increase in power consumption of equipment, 10KV voltage level diesel generator sets have become more and more widely used. 10KV generator sets also have self-starting functions, but they need to be paralleled first and then connected to the mains ( transform...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): H02J9/08
Inventor 程鸣辉胡坚钧曹国水蒋姚雄
Owner HUAXIN CONSULTATING CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Eureka Blog
Learn More
PatSnap group products