Urban bridge rapid demolition and reconstruction construction method based on gantry crane

A construction method and gantry crane technology, which are applied in bridge construction, bridges, bridge maintenance, etc., can solve the problems such as the long time required to re-build the temporary structure of the new bridge, the inability to meet the rapid reconstruction of urban trunk roads and bridges, and the inability to realize the overall removal process. Achieve the effect of meeting navigation restrictions and environmental protection, saving construction costs, and simplifying construction

Pending Publication Date: 2021-12-31
中铁二十二局集团第三工程有限公司 +1
View PDF6 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] Some concrete-filled steel tube tied arch bridges built in the early days of urban main roads cannot meet the existing traffic demand with the increase of operation time, traffic volume and load level, and often need to be demolished and rebuilt in situ
[0003] However, some bridges are limited by inland river navigation conditions and ecological environmental protection requirements, and the overall removal and blasting methods cannot be realized. Usually, the old bridges can only be demolished by reverse demolition. This method requires a long construction period and the demolition of the bridge The equipment and facilities in the process cannot be used during the construction of the bridge, and it will take a long time to re-build the temporary structure of the new bridge, which cannot meet the needs of rapid reconstruction of urban arterial bridges

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Urban bridge rapid demolition and reconstruction construction method based on gantry crane
  • Urban bridge rapid demolition and reconstruction construction method based on gantry crane
  • Urban bridge rapid demolition and reconstruction construction method based on gantry crane

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0048] The technical solutions of the present invention will be further described below in conjunction with the accompanying drawings and through specific implementation methods.

[0049] A construction method for rapid demolition and reconstruction of urban bridges based on gantry cranes, comprising the following steps:

[0050] Step S1: Construct the auxiliary road bridge and divert the traffic to the auxiliary road bridge

[0051] The bored piles of the auxiliary road bridge are being constructed, and the caps and columns of the auxiliary road bridge are poured. The steel box girder of the auxiliary road bridge is hoisted and welded, and erected from the two side spans to the middle span, and then the traffic is diverted to the auxiliary road bridge ;

[0052] Step S2: Erection of the main bridge gantry crane

[0053] On both sides of the old bridge, the crawler crane cooperates with the vibrating hammer to insert the steel pipe pile foundation 6 of the gantry crane. Afte...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses an urban bridge rapid demolition and reconstruction construction method based on a gantry crane, and belongs to the field of bridge engineering. The method comprises the steps that S1, an auxiliary road bridge is constructed, and traffic is guided and changed to the auxiliary road bridge; S2, a main bridge gantry crane is erected; S3, a bridge dismantling bracket is erected; S4, an arch rib support is erected; S5, an accessory structure and a bridge deck system of the old bridge are detached; S6, a rope saw is adopted for cutting the bridge flange plate and hoisting away the bridge flange plate; S7, after the suspender is dismantled, the suspender is transported out of the construction site; S8, arch ribs are cut and hoisted away in a segmented mode through a gantry crane; S9, the main beam is cut, decomposed and hoisted away in a segmented mode through a gantry crane; and S10, the old pier platform steel sheet pile cofferdam is constructed and decomposition and hoisting are performed on a lower structure; according to the rapid dismantling and reconstruction method, ecological dismantling of an old bridge and rapid erection of a new bridge are achieved through repeated utilization of the bridge dismantling gantry crane, the requirements of navigation limitation and environmental protection are met, and normal traffic of urban trunk traffic is guaranteed.

Description

technical field [0001] The invention relates to the field of bridge engineering, in particular to a construction method for rapid demolition and reconstruction of urban bridges based on gantry cranes. Background technique [0002] Some concrete-filled steel tube tied arch bridges built in the early days of urban main roads cannot meet the existing traffic demand with the increase of operation time, traffic volume and load level, and often need to be demolished and rebuilt in situ. [0003] However, some bridges are restricted by inland river navigation conditions and ecological environmental protection requirements, and the overall removal and blasting methods cannot be realized. Usually, the old bridges can only be demolished by reverse demolition. This method requires a long construction period and the demolition of the bridge The equipment and facilities in the process cannot be used during the construction of the bridge, and it will take a long time to re-build the tempo...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E01D24/00E01D21/00
CPCE01D22/00E01D21/00
Inventor 刘四德姚正斐高勇黄志猛孙金烈邓朝友赵俊杰万成福
Owner 中铁二十二局集团第三工程有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products