A construction method and prefabricated technology, applied in tunnels, tunnel linings, shaft equipment, etc., can solve problems such as difficulty in guaranteeing construction quality, deformation of the tunnel bottom, and slow rescue speed, so as to reduce labor and mechanical costs and strengthen vertical and horizontal connections , The effect of speeding up the construction progress
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0041] In a typical embodiment of the present disclosure, such as Figure 1-Figure 7 As shown, a cavity-assembled tunnel invert is proposed.
[0042] The prefabricated tunnel inverted arch mainly includes inverted arch blocks arranged in sequence along the tunnel extension direction, and the inverted arch block is composed of a plurality of prefabricated blocks, thereby forming multiple rows of prefabricated blocks arranged in sequence along the tunnel extension direction;
[0043] The inverted arch adopts a prefabricated assembly type, and the components are made in the prefabricated field, and the quality and strength are reliable, which replaces the traditional invert arch and sets the trestle bridge cast-in-place method, reduces the labor and machinery cost in the traditional inverted arch construction, and accelerates the overall construction progress of the tunnel. .
[0044] The inverted arch block comprises the first prefabricated block, the second prefabricated block...
Embodiment 2
[0072] In another exemplary embodiment of the present disclosure, as Figure 1-Figure 7 As shown, a construction method of a cavity-assembled tunnel inverted arch is proposed, using the cavity-assembled tunnel inverted arch as described in Embodiment 1.
[0073] Include the following steps:
[0074] Carry out pretreatment to the inverted arch block, carry out pretreatment to the tunnel, and arrange the inverted arch cushion;
[0075] Each inverted arch block is hoisted successively, and the inverted arch block is installed successively along the longitudinal extension direction of the tunnel;
[0076] Align the passage in the inverted arch block, connect adjacent inverted arch blocks successively;
[0077] A tunnel leveling layer is constructed on the top surface of the inverted arch block, and other auxiliary facilities are arranged.
[0078] Specifically, in conjunction with each structure in Example 1, the construction process is described in detail:
[0079] The first ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com