Prestressed unbonded anchor rod steel bar, anchor rod and construction method

A prestressed, non-bonded technology, used in the installation of anchor rods, infrastructure engineering, sheet pile walls, etc., to save construction time, save costs, and improve project quality and efficiency.

Pending Publication Date: 2020-09-22
安徽俊力建设有限公司
View PDF2 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0015] The applicant is prior: CN2017103638836 a prefabricated prestressed anchor rod and its construction method; CN2017103638836 a construction method for overcoming the deformation of the anti-floating fixed diameter anchor head or expansion head anchor rod system, but there are still improvements in the prestressed anchor rod place

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Prestressed unbonded anchor rod steel bar, anchor rod and construction method
  • Prestressed unbonded anchor rod steel bar, anchor rod and construction method
  • Prestressed unbonded anchor rod steel bar, anchor rod and construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0081] As shown in the figure, the example of parts in the figure: base 1, concrete cushion 2, anchor rod after pouring or called anchor rod 3, the main reinforcement prepared by concrete or mortar pouring or the pipe column of the outer layer of the finished thick steel bar, that is, the anchor rod Concrete or mortar for the outer layer of steel bars 3-2, fixed plate or bearing plate 3-4, nuts for applying prestress 3-3, anti-corrosion grease layer 3-6, plastic film sleeve 3-5, limiter 11, flange The nut assembly 16-1 is used to fix the anchor rod steel bar (main reinforcement or finish-rolled thick steel bar) 3-1 on the base plate. Prestressing of rolled steel bars. Waterstop rubber strip 4, flange nut 16, concrete bottom plate 8, concrete bottom plate reinforcement 8-1, bottom plate cushion 8-2, and steel cage 10 can be straight-through or enlarged head structure, and the figure is variable diameter The enlarged diameter steel cage structure. Grouting body 12, nut connect...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a prestressed unbonded anchor rod steel bar. The prestressed unbonded anchor rod steel bar comprises a main steel bar body serving as a basic force bearing structure, the main steel bar body is a finish rolling steel bar or a common steel bar, an anti-corrosion grease layer is arranged on the surface of the main steel bar body, and a plastic film sleeve is arranged outside the anti-corrosion grease layer. The number of the main steel bar bodies is one or one to five, and the main steel bar body is of a main steel bar structure formed by connecting segmented reinforcing steel bars through connecting nuts. According to the prestressed anchor rod prepared from the unbonded anchor rod steel bars, the unbonded main steel bars are directly cast into the prestressed anchorrod through concrete, or the lower end of the prestressed anchor rod is connected with grouting bodies or concrete of expanded heads; the grouting body or concrete of the expanded head is internally wrapped with a steel reinforcement framework or a bag, wherein the steel reinforcement framework comprises one or more steel reinforcements, a steel reinforcement cage with a common structure and a variable-diameter steel reinforcement cage; an anti-floating tensile anchor rod of a concrete prefabricated pipe column is prepared when a steel reinforcement cage and a variable-diameter steel reinforcement cage of a common structure are adopted; one or more reinforcing steel bars are connected by using one or more reinforcing steel bar anchor rod reinforcing steel bars; and one or more reinforcingsteel bars or reinforcement cages are still arranged in the center of the bag.

Description

technical field [0001] The invention relates to a novel prestressed anchor rod, in particular to a pre-tensioned or post-tensioned anti-floating and tensile anchor rod and its construction method. Anti-floating tensile steel anchors and their application technologies prepared with pre-tensioned or post-tensioned prestressed anti-floating and tensile unbonded steel bars, and combined with various anchor heads such as straight-through or enlarged heads to form a post-tensioned prestressed anchor system. To overcome the anti-floating deformation, the rod body can be elastically deformed in the free section, and relates to an anchor rod system and even a pressure-resistant pile system that overcomes the anti-floating straight-through or enlarged headband to apply prestress. Background technique [0002] The straight-through or enlarged head prestressed bolt technology is a new type of underground engineering application technology, which is in line with the spirit of "energy sav...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/74E02D31/00E02D31/12E21D21/00E02D17/04E02D17/20
CPCE02D5/74E02D31/00E02D31/12E21D21/0006E21D21/0013E21D21/0026E02D17/04E02D17/20
Inventor 王林陶刚王军
Owner 安徽俊力建设有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products