Construction method of hollow floor slab
A construction method and technology of hollow floor slabs, which can be applied to floor slabs, building components, buildings, etc., can solve the problems of height limitation of large-span building space, closed building space, heavy weight, etc., and achieve light weight, open building space, and The effect of weight reduction
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0045] A construction method for a hollow floor slab, comprising the following steps:
[0046] Step 1, construction preparation;
[0047] Step 2, formwork installation, calculate the formwork support system of the gypsum filling box, in which, the saturated bulk density of the gypsum filling box must be fully considered during the calculation process, and the support system should be erected strictly according to the calculation results. Carry out two-way arching; encrypt the supporting distance of the steel pipe frame under the concealed beam and column cap, and encrypt the supporting distance of the steel pipe frame under the floor according to the special construction plan;
[0048] Step 3, measure and set out the line, set out the line according to the layout drawing, release the position line of the rib beam, and determine the installation position of the gypsum filling box;
[0049] Step 4, steel bar binding, steel bar installation according to the construction drawing,...
Embodiment 2
[0064] In order to make the technical solution in this application more complete and detailed, further supplementary explanations are made on the basis of the above-mentioned embodiment 1, so that the technical means used in this application are disclosed more fully, wherein the technical characteristics of the supplementary part are: In step 1 above, the construction preparation is divided into the following processes:
[0065] S1, according to the size of the drawing and the model specification of the gypsum filling box, prepare a material entry plan and entrust a professional manufacturer to produce it;
[0066] S2. Organize construction technicians to conduct targeted learning, conduct technical and safety disclosures for teams of different types of work, and prepare for labor;
[0067] S3, before construction, divide a special material site on site, and process the site according to the relevant regulations on the stacking of gypsum filling boxes;
[0068] S4. After the ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com