Eureka AIR delivers breakthrough ideas for toughest innovation challenges, trusted by R&D personnel around the world.

Construction process of gob side roadway protection in medium-thickness coal seam coal face

A technology for coal mining face and construction technology, applied in ground mining, mining equipment, earthwork drilling and other directions, can solve problems such as roadway damage, roof pressure is not released, high maintenance costs, etc., to solve the problem of gas overrun, The effect of reducing the physical labor of employees and improving labor efficiency

Inactive Publication Date: 2019-11-12
SICHUAN HUAYINGSHAN LONGTAN COAL
View PDF8 Cites 6 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] In the past, some mines in China have researched and realized small coal pillars or even no coal pillars mining, but there are many roadways with high stress in the surrounding rock, large deformation of the roadway, high maintenance cost when the roadway is in use, and the small coal pillars left are completely crushed and deformed. 1. If the filling method realizes no coal pillars, the filling body will bulge and deform, and even need to re-expand the coal side, and the maintenance cost of the roadway will even exceed that of a newly dug roadway. Due to the uncontrollable direction of the blasting method, the pressure relief may even cause damage to the roadway. Research and tests have shown that the above problems can be solved by using directional concentrated energy blasting for roof cutting and pressure relief.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction process of gob side roadway protection in medium-thickness coal seam coal face

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0031] This embodiment discloses a construction process for gob-side roadway protection in a medium-thick coal seam coal mining face, including the following steps:

[0032] S1 supports the single hydraulic prop 4 on the side of the reserved roadway 1 close to the coal mining face 2 to cooperate with the I-shaped steel 5, and the construction is completed within 20m ahead of the working face, and the vertical direction of the I-shaped steel 5 to the coal mining face 2 is evenly arranged , the distance between two adjacent I-beams 2 is 0.6m-1.0m, preferably 0.7m-0.9m; a row of anchor cables 6 is laid on the side of the reserved roadway 1 close to the coal mining face 2, and the anchor cables 6 pass through Anchor beams are connected and combined with channel steel 7 for roof protection, and the construction is completed within 20m to 50m of the advanced working face. Channel steel 7 is 14# channel steel, and the distance between anchor cables 6 is 1 to 2m, preferably 1.2m to 1.8...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the technical field of coal mining, and provides a construction process of gob side roadway protection in a medium-thickness coal seam coal face. The construction process comprises the steps that a single hydraulic prop is supported in a reserved roadway to be matched with an I-shaped beam, and an anchor cable is erected to be matched with a channel steel protection roof;a presplitting blasting hole is formed in the roof; a single hydraulic prop is supported at the fork of the reserved roadway and the coal face to be matched with the I-shaped beam; the I-shaped beam is erected in the lagging part of the coal face, a steel bar mesh and a metal mesh are sequentially paved along the roadway trend, then the single hydraulic prop is supported to be matched with the I-shaped beam, and then a diagonal prop is supported to strengthen the support of the I-shaped beam; outside the lagging area of the coal face, the single hydraulic prop is retracted; the roadway is treated with shotcrete in full section; and a grouting pipe is pre-embedded under the roof of the coal face for grouting. According to the construction process, the technical effects that the resource recovery rate can be increased, the production cost is saved, the impact on the dynamic pressure of the adjacent roadway is reduced, the secondary maintenance amount of the roadway is decreased, and thelabor intensity of employees is lowered are achieved.

Description

technical field [0001] The invention belongs to the technical field of coal mining, and in particular relates to a construction technology for gob-side roadway protection in coal mining working faces of medium-thick coal seams. Background technique [0002] In the past, some mines in China have researched and realized small coal pillars or even no coal pillars mining, but there are many roadways with high stress in the surrounding rock, large deformation of the roadway, high maintenance cost when the roadway is in use, and the small coal pillars left are completely crushed and deformed. 1. If the filling method realizes no coal pillars, the filling body will bulge and deform, and even need to re-expand the coal side, and the maintenance cost of the roadway will even exceed that of a newly dug roadway. Due to the uncontrollable direction of the blasting method, the pressure relief may even cause damage to the roadway. The research and test show that the roof cutting and press...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E21C41/18E21D15/44E21D20/00E21D11/14E21D11/15E21D11/10E21F15/00F42D3/04
CPCE21C41/18E21D11/10E21D11/14E21D11/152E21D15/44E21D20/00E21F15/005F42D3/04
Inventor 范凯王强何立菊卓军汪胜郭富生
Owner SICHUAN HUAYINGSHAN LONGTAN COAL
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Eureka Blog
Learn More
PatSnap group products