Limited bracket construction method of large-span S-shaped steel box girder
A construction method and steel box girder technology, applied in bridges, bridge materials, bridge construction, etc., can solve the problems of high cost and long construction period, and achieve the effects of reducing economic costs, short construction period, and fast material turnover
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0062] Specific embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings. It should be understood that the specific embodiments described here are only used to illustrate and explain the present invention, and are not intended to limit the present invention.
[0063] Refer to attached Figure 1-6 , a method for constructing a long-span S-shaped steel box girder with few supports, adopting a prefabricated steel box girder as the upper main girder structure of the bridge, the main girder is generally S-shaped, and the steel box girder includes 14 subsections of prefabricated steel box girders, After being assembled into seven sections at the construction site, they are hoisted and fixed. The specific construction methods are as follows:
[0064] (1) Prefabrication and assembly of steel box girders: complete the assembly of temporary supports and prefabricated steel box girders, and complete the preparation of climbing ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com