Installation device for a prefabricated bridge deck
An installation device and prefabricated bridge technology, which is applied to bridges, bridge parts, bridge construction, etc., can solve the problem that the bridge deck cannot be hoisted and installed, and achieve the effects of shortening the construction period, convenient operation, and improving installation efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0024] (1) Processing and installation of round steel pipe support: The round steel pipe support is processed by Φ299*10mm round pipe, and the height can be adjusted by itself due to the influence of longitudinal and transverse slopes to ensure that the top surface is level or the slope is not greater than 1%. A 400*400*20mmQ235 steel plate is welded at the upper and lower ends. The support of round steel pipes is manually transported and installed, and its lower end is welded to the overhanging eaves of the steel box girder with a distance of 4.65m. Among them, the round steel pipes can be replaced by materials such as I-beams.
[0025] (2) Processing and installation of longitudinal slideway beams: The longitudinal slideway beams are processed with 45b I-beam, and the length of a single set is 12m. The I-beam is welded with a stiffening plate along the longitudinal interval of 50cm. The stiffening plate is processed by Q235 steel plate with an upper bottom of 410mm, a lower ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com