Demolition blasting method for prestress concrete cantilever trussed arch bridge

A cantilever truss and concrete technology, which is applied in blasting, building maintenance, construction, etc., can solve problems such as high cost and inability to fully realize design intent

Inactive Publication Date: 2012-12-26
GUIZHOU XINLIAN BLAST ENG GRP
View PDF6 Cites 16 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Traditional bridge demolition blasting generally adopts single shallow hole blasting, hydraulic blasting or concentrated energy cutting blasting for demolition, but the prestressed reinforced concrete cantilever truss arch bridge is a composite structure, and most of the components are box-shaped structures with thin walls. Hole or multi-point hydraulic blasting schemes cannot fully realize the design intent, and the cost of fully adopting energy-concentrated wire cutting blasting schemes is relatively high

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0009] Bijie Guihua Bridge is located in Guihua Village, Bijie City, Guizhou Province. It is an important highway bridge on the high-grade highway between Guizhou and Bijie. It was completed and opened to traffic in 1994. Due to the imperfect supervision mechanism during the bridge construction stage, the quality has not been effectively guaranteed. Serious quality hidden dangers, and the rapid economic development was not expected in the design, the traffic flow is large, and there are many overloaded and over-limited vehicles, resulting in the bridge needing to be demolished by blasting before its service life.

[0010] (1) Using the method of gathering energy line cutting blasting, firstly cut all the prestressed anchor cables on the main arch of the bridge and the lower chord girders at the foot of the main hole at the same time. The amount of charge is 40g / cm, and the Hexokine explosive is selected, so as to avoid the foundation of the huge tensile force generated when th...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a demolition blasting method for a prestress concrete cantilever trussed arch bridge. The demolition blasting method comprises the following steps: an energy-gathering line cutting blasting method is adopted; firstly, all prestress anchor cable reinforcing steel bars and lower chord girder reinforcing steel bars in a main hole pin section on the main arch of the bridge are cut at the same time; the dose of the thread-loaded explosive of an energy-gathering explosive bag for cutting the pre-stress anchor cable reinforcing steel bars is 40g / cm; a multi-point water pressure blasting method is adopted for demolishing supporting stand columns and arch support stand columns on the piers of the bridge and a hollow body of an edge hole steel structure beam; water pressure explosive bag groups are arranged according to the required positions and heights of cutting openings based on the bridge collapse technology; and the arch top of the bridge and a solid body section between the two edge hole steel structure beams close to a bridge abutment are demolished by a drilling blasting method. By virtue of the above method, the steel structure beam, the arch support stand columns and the plier stand columns are completely demolished, the concrete is crashed and separated, and the bridge is collapsed in an unstable state.

Description

technical field [0001] The invention relates to a blasting method for demolition of highway bridges, in particular to a blasting demolition method for prestressed concrete cantilever truss arch bridges. Background technique [0002] Prestressed concrete cantilever truss arch bridge is a new type of structural bridge developed in the 1980s. This type of structural bridge has better stress conditions than arch truss bridges and has the characteristics of large span. It is one of the main development directions of long-span bridges. In recent years, due to the construction of water conservancy facilities, road widening, etc., there are a large number of such structural bridges that need to be demolished. Traditional bridge demolition blasting generally uses a single shallow hole blasting, hydraulic blasting or energy-gathering cutting blasting for demolition, but the prestressed reinforced concrete cantilever truss arch bridge is a composite structure, and most of the component...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01D24/00F42D3/02
Inventor 池恩安魏兴赵明生沈晓碧刘庆沈晓松胡浩川
Owner GUIZHOU XINLIAN BLAST ENG GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Eureka Blog
Learn More
PatSnap group products