Super sized iron piece high precision mounting construction method
A construction method and ultra-large technology, applied in the processing of building materials, construction, building construction, etc., can solve the problems of many anchors, increase construction costs, and easy deformation of iron parts, so as to reduce construction costs and achieve good use effects , Guarantee the effect of installation accuracy
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment
[0024] Example: High-precision installation and construction method for super-large iron parts, construction process: cutting and dividing iron parts and steel plates → opening iron parts and steel plates → making and installing iron parts and anchors → pouring concrete to fix anchors → hoisting and placing iron parts and steel plates → Welding anchors and steel plates of each piece of iron → Concrete pouring; the specific steps are as follows:
[0025] (1) Blocking and opening of iron parts:
[0026] Cutting of iron parts into blocks:
[0027] Divide the super-large iron steel plate into blocks, and use a cutting machine to cut the boards. There are zigzag and other curved notches between each block. Try to avoid anchors and places where the steel bars under the iron parts are denser, and avoid other reserved holes such as pouring holes on the surface of the iron parts.
[0028] Iron parts opening:
[0029] Welding anchor holes, concrete pouring holes, vent holes, and vibr...
example
[0045] Yantai Raffles 20,000 tons fixed gantry crane concrete foundation project, the J-4 roof size is 30.6×8.6×4m, the concrete strength is C50, the total weight of the roof embedded iron parts is 112 tons, and the roof M-D iron parts size is 18800×2000×50mm , including anchors weighing 18 tons, anchors are mainly 400×400×40×40mm welded H-shaped steel (length 2.8m), auxiliary anchors are L160×16 angle steel, HRB400 steel bars, installation height 70m, installation requirements levelness ± 2mm , Axis deviation ± 5mm. The M-D iron parts are hoisted in three pieces, the lengths are 6200mm, 6000mm, and 6600mm respectively. Anchor holes, pouring holes, and vent holes are reserved on the surface of the iron parts. Each reserved hole is a half-groove, and each block is a full slope mouth. The CNC plasma cutting machine is used to process the steel plate, the 6t pulling rod hoisting iron parts, the total station positioning iron parts, and the CO2 gas shielded arc welding iron parts...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com