[0011] (1) When encountering a high
groundwater level or pressurized water, the standard column hammer cannot be constructed due to water and mud entering the
pipe; Under the double action of negative pressure and viscous force, it will also make it very difficult to
pull up the standard column hammer, especially in saturated sandy soil, if it is forced to
pull up, it will easily cause water ingress or sand gushing in the
pipe, making it difficult to continue the construction; What is more serious is the influence of factors such as the gap between the true
diameter of the standard column hammer and the inner
diameter of the outer
pipe. When the standard column hammer freely falls to tamp the filling material, the air resistance,
water resistance, mud resistance, etc. generated will directly lead to the actual tamping. The force effect is distorted and not easy to be found, resulting in discrete pile bearing capacity and low reliability of construction quality
Therefore, the original carrier pile can only be constructed under dry conditions without
groundwater;
[0012] (2) The potential of some soil
layers has not been fully utilized: the pile foundation generally chooses a higher bearing capacity, thicker and continuous soil layer as the bearing layer, but for those without a better natural bearing layer or better natural bearing When the depth of the layer is deep and it is not easy to use, choosing a soil layer with a relatively good bearing capacity can also achieve a higher bearing capacity after reinforcement treatment is a major potential
advantage of the carrier pile, which is ignored.
It is also one of the reasons for the limited applicability;
[0013] (3) The optional range of pile
diameter and pile length is small, which is also the main cause of limited applicability: the diameter of the standard column hammer determines the diameter range of the pile; and the
effective height of the pile frame limits the maximum length of the pile
Due to the constraints of technology and equipment, the general carrier pile can only be used for the construction of short piles with small diameters;
[0014] (4) Using standard column hammers to carry out carrier pile construction has low tamping frequency and low construction efficiency, and the work efficiency is even lower when the ground conditions are affected. The existing technology uses double hammers, pile hammers or vibratory hammers for construction to improve construction efficiency. , but the upper and lower arrangement of the double hammer occupies a large part of the
effective height of the pile frame, so that the actual pile length is limited, and it can only be adapted to the construction of small pile diameters and short piles; due to the requirement that "the length of the inner pipe is greater than the length of the outer pipe", It is difficult to implement waterproof and
silt prevention measures under high
water level conditions, and the quality of piles is not easy to control; during the construction of double hammer operations, the total
mass and height of the hammers
pose a challenge to the stability of the
pile driver and increase the difficulty of operation. , requires higher technical personnel;
[0015] (5) In the prior art, the three-strike penetration is the key index to determine the bearing capacity of the carrier. When the pile hammer or vibratory hammer is used as the power to carry out the construction of the carrier pile, because the models of the pile hammer or vibratory hammer used are not uniform , so that the actual hammering force is not the same, but it is not easy to keep consistent with the three-strike penetration requirements, resulting in no basis for design and construction, and difficult to control the construction quality;
[0016] (6) As a special construction equipment, not only the investment is large but also the function is single, and the
utilization rate of the equipment is limited, resulting in waste of investment;
[0017] (7) Low construction efficiency: hydraulic shaking or rotary methods are used to form holes, regardless of the speed of sinking and pulling pipes; the grabbing bucket takes a small amount of soil each time and the frequency is low; the
pile driver is time-consuming and laborious to move in place;
[0018] (8) High cost and few optional pile diameter specifications: due to the investment in equipment and steel casings, general construction units lack economic strength, and it is difficult to purchase casings of various diameters and specifications, so the pile diameters are limited to a certain extent; Due to the limitations of equipment and equipment, it cannot be applied to the construction of small piles;
[0019] (9) Huge equipment: a large construction site is required for construction, and the distance from the boundary of the construction site to the center of the side pile is also required to be relatively large. It is difficult to survive today when the construction land is very expensive.