Construction method of open caisson
A construction method and caisson technology, applied in caissons, foundation structure engineering, construction, etc., can solve problems such as small caisson anti-heaving coefficient, cracking, uneven settlement of structures, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0083] Example 1, such as figure 1 , image 3 Shown, a kind of caisson construction method comprises the following steps:
[0084] (1) Construction preparation work, on-site layout of temporary structures, mechanical equipment and construction water and electricity lines according to the general layout plan; set up gantry piles around the caisson, and use lime powder to draw the well central axis and foundation pit outline, As the basis for caisson fabrication and sinking positioning; it should be noted that in order to meet the requirements of construction machinery and equipment and civilized construction, a construction access road is built in the construction enclosure. Ash three slag, then pave 20cm concrete; heavy-duty vehicles and crane driving area first lay 25cm thick fly ash three slag, and then lay 25cm concrete; the inner surface of concrete is Φ8@250 two-way reinforced mesh. Along the side of the caisson, a steel bar processing plant, formwork assembly site, and...
PUM
Property | Measurement | Unit |
---|---|---|
Ultimate bearing capacity | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com