Underwater terrain inversion method for coal mining subsidence ponding area by utilizing InSAR monitoring data
A technology for coal mining subsidence area and monitoring data, which is applied in the direction of utilizing re-radiation, reflection/re-radiation of radio waves, measuring devices, etc. Reduce the cost of manpower measurement, obtain the effect of convenient and high precision
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0035] see Figure 1-2 As shown, this embodiment is a method for inversion of underwater terrain in coal mining subsidence water accumulation area using InSAR monitoring data, including the following steps:
[0036] S1. Obtain two sets of InSAR data before and after the subsidence of the surface above the coal mining face, use the InSAR data before the subsidence as the main image, and the InSAR data after the subsidence as the auxiliary image, and use the InSAR processing technology to combine the two InSAR images Acquire the DEM of the unwatered area in the coal mining subsidence area through standardization, interference processing, flattening, and phase unwrapping, and use H 1 (x,y) 未积水 Indicates that (x,y) 未积水 is the coordinates of the point in the subsidence area without water accumulation, H 1 is the elevation of the post-subsidence point;
[0037] S2. Generate the DEM before the subsidence of the coal mining subsidence area; the generation method of the DEM before ...
Embodiment 2
[0052] see Figure 1-2 As shown, this embodiment is a method for inversion of underwater terrain in coal mining subsidence water accumulation area using InSAR monitoring data, including the following steps:
[0053] S1. Obtain two sets of InSAR data before and after the subsidence of the surface above the coal mining face, use the InSAR data before the subsidence as the main image, and the InSAR data after the subsidence as the auxiliary image, and use the InSAR processing technology to combine the two InSAR images Acquire the DEM of the unwatered area in the coal mining subsidence area through standardization, interference processing, flattening, and phase unwrapping, and use H 1 (x,y) 未积水 Indicates that (x,y) 未积水 is the coordinates of the point in the subsidence area without water accumulation, H 1 is the elevation of the post-subsidence point;
[0054] S2. Generate the pre-subsidence DEM of the coal mining subsidence area; the generation method of the DEM before the sub...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com