Method for treating boulders in reinforced zone of starting end
A treatment method and technology for boulders, which is applied in the field of boulder treatment in the reinforcement area at the starting end, can solve problems such as equipment damage, large impact on shield construction, and impact on construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0036] A method for treating boulders in the reinforcement area at the originating end. According to the conditions of the boulders in the reinforcement area at the originating end, three boulder processing methods, namely, blasting, mechanical treatment by rotary drilling, and crushing of submerged holes, are compared and analyzed. It is determined that the boulder treatment in the reinforcement area at the starting end mainly adopts the construction method of submerged hole density hole crushing.
[0037] Further, the specific method of comparative analysis is as follows:
[0038] (1) Analysis of the impact on reinforcement, main structure, and outer plain wall
[0039] Due to the particularity that the boulder at the starting end is inside the reinforcement body and is close to the main structure and the outer wall, the treatment of the boulder in the reinforcement area of the starting end must fully consider the impact of the boulder treatment on the reinforcement body a...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com