A construction method and shaft technology, applied in shaft equipment, sinking, earthwork drilling and mining, etc., can solve the problems of poor safety and quality, long single cycle time, and difficult maintenance in the later stage, so as to eliminate waterproofing and drainage Leakage, short single cycle time, good waterproof and drainage effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0034] Excavation of shaft wellhead site and wellhead section;
[0035] After the wellbore center is calibrated, the wellhead site is excavated around the shaft to meet the needs of the wellbore construction.
[0036] The wellhead is 1.0m above the ground surface, and the vertical shaft is equipped with a C30 reinforced concrete structure well ring and lock ring within a range of 5m from the wellhead, and then the wellhead is backfilled with C15 rubble concrete.
[0037] After the wellhead site is leveled, mechanical equipment is used to excavate the surface soil section of the shaft wellhead. The excavation depth is 4m, and the excavation is divided into two layers. The excavation depth of each layer is 2m.
[0038]The wellhead section of the shaft is excavated and formed, and the lock ring is applied after cleaning the bottom. Erect the steel bars of the lock ring, and after the erection of the steel bars, support the inner and outer formwork of the lock ring, pour the conc...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com