[0015] As shown in the figure, in the foundation pit, there are overlapping three-axis mixing piles 1 and support piles 2 arranged coaxially at fixed intervals, and a steel bar structure is set to form a continuous wall.
[0016] The three-axis mixing piles overlap and overlap to form a three-axis mixing wall, and the three-axis mixing pile machine is used to construct the water-stop curtain of the foundation pit. The pile diameter of the three-axis mixing piles is ¢650mm, and the pile spacing is 0.9m. For compound-stirring connection construction, the length of the pile entering the strong weathered rock shall not be less than 1.0m. The three-axis mixing pile adopts 42.5 grade ordinary Portland cement, the cement content is not less than 20%, and the soil weight is 1.9T / m 3 Considering comprehensively, the water-cement ratio should be 1:1. The 28d unconfined compressive strength of the cement-soil wall is not less than 0.8Mpa. During the construction process, due to overtim...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com