A construction method and site technology, applied in the construction field of the relocation and protection of building sites, can solve problems such as damage and historical sites are not effectively protected, and achieve the effect of ensuring effectiveness and facilitating hoisting and construction.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0064] Embodiment: (the site area of this embodiment is an L-shaped structure)
[0065] 1) Pipe jacking construction: Pass the steel pipe through the pipe jacking equipment and place it below the soil in the ruins area, so as to separate the soil in the ruins area from top to bottom.
[0066] Specifically: Excavate the pipe jacking area on the side of the ruins area in advance, and pour a concrete cushion in the pipe jacking area; Penetrate to the position below the ruins area.
[0067] 2) Construction of the jacking track foundation: According to the in-situ test of the soil on site, the characteristic value of the bearing capacity of the soil foundation in the site area is about 60KPa, that is, the soil properties are poor; if a large area is excavated at the same time, the remaining part of the soil will The additional stress to be borne is large, which will cause great deformation and even lead to soil collapse, endangering the safety of the ruins. Therefore, the ruins ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com