Method for preventing long empty pile part of prestressed pipe pile from falling
A prestressed pipe pile and anti-fall technology, which is applied to sheet pile walls, processing of building materials, infrastructure engineering, etc. Long-empty pile foundation loosening and falling, etc., achieve the effect of significant safety protection effect, simple construction method, and remarkable anti-fall effect.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0026] A method for preventing falling of prestressed pipe pile long empty pile parts, the specific method steps are as follows:
[0027] Step 1: The technical personnel in charge of the project weave the special construction plan for the fall prevention of the long and empty prestressed pipe piles, and weave a targeted emergency plan, and conduct technical disclosure work to the construction leader and the construction team leader before construction;
[0028] Step 2: The technicians in charge of the project calibrate the construction data, and inspect the prestressed pipe pile long empty pile and other building material components transported to the construction site;
[0029] Step 3: After the construction site is staked out, the site is pretreated, and compacted with a small road roller, and the pile position is accurately positioned and recorded;
[0030] Step 4: Excavate the foundation pit at the construction site of Step 3, foundation pit pretreatment: a, foundation pit...
Embodiment 2
[0040] A method for preventing falling of prestressed pipe pile long empty pile parts, the specific method steps are as follows:
[0041] Step 1: The technical personnel in charge of the project weave the special construction plan for the fall prevention of the long and empty prestressed pipe piles, and weave a targeted emergency plan, and conduct technical disclosure work to the construction leader and the construction team leader before construction;
[0042] Step 2: The technicians in charge of the project calibrate the construction data, and inspect the prestressed pipe pile long empty pile and other building material components transported to the construction site;
[0043] Step 3: After the construction site is staked out, the site is pretreated, and compacted with a small road roller, and the pile position is accurately positioned and recorded;
[0044] Step 4: Excavate the foundation pit at the construction site of Step 3, foundation pit pretreatment: a, foundation pit...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com