A method for drilling and pulling out prestressed anchor cables for foundation pit support

A prestressed anchor cable and foundation pit support technology, which is applied in excavation, foundation structure engineering, construction, etc., can solve problems such as low reliability, long construction period, and anchor cable breakage, and achieve flexible adjustable angles and land occupation Small area, avoiding the effect of danger source

Active Publication Date: 2020-06-23
SHENZHEN GEOKEY CONSTR GRP CO LTD
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] The support of deep foundation pits often adopts the form of enclosure piles + prestressed anchor cables. After the basement is backfilled, the prestressed anchor cables of the enclosure structure lose their function, but because they invade the underground space outside the original foundation pit, the surrounding buildings ( For example, when the urban subway tunnel adopts the shield method to pass through the construction, or the construction of the surrounding new basement enclosure structure, the prestressed anchor cables of the previous construction will cause huge obstacles to the construction, adding Increased construction difficulty and safety risks, increased construction economic costs and construction period costs
[0003] At present, in addition to the retrievable prestressed anchor cable, the main method for pulling out the intruded prestressed anchor cable is to release the locking of the tension end, and apply the prestress by using a through-hole jack until the anchoring force exceeds the anchor cable and the anchor cable fails. Pulling out, this method cannot control the critical point of the anchoring force failure of the anchor cable, there may be a situation where the anchor cable is broken and the anchor section cannot be pulled out, and the anchor section is loose or the ejection force generated by the instantaneous prestress of the anchor cable breaks There are great potential safety hazards for the operators, and the reliability rate is low and unsafe; the second is to use manual excavation of the shaft to cut off the anchor cables in sections and pull them out. This method needs to occupy a certain amount of work space on the ground outside the enclosure structure , it is not suitable for use in areas with heavy traffic or areas with structures, and there is uncertainty in the control of the intersection between the vertical excavation direction and the anchor cable construction direction, resulting in high safety risks, long construction period, and high cost; the third is to use shield tunneling The open-cup cable-cutting method requires modification of the shield machine’s cutter head and cutters, and takes a long time to process, posing a greater safety hazard
[0004] Ordinary prestressed anchor cable removal methods cannot meet today's construction requirements. How to pull out the failed abandoned prestressed anchor cables when the basement has not been backfilled and there is still work space, without causing disturbance to the surrounding environment and ensuring the prestressed anchor cables. The success rate of pulling out the cable and the safety of the operators have become the primary problems to be solved by this method.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A method for drilling and pulling out prestressed anchor cables for foundation pit support
  • A method for drilling and pulling out prestressed anchor cables for foundation pit support
  • A method for drilling and pulling out prestressed anchor cables for foundation pit support

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0047] The present invention will be further described below in conjunction with the drawings and embodiments.

[0048] In the following, the concept, specific structure and technical effects of the present invention will be clearly and completely described in conjunction with the embodiments and the drawings to fully understand the purpose, features and effects of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all of them. Based on the embodiments of the present invention, other embodiments obtained by those skilled in the art without creative work belong to The scope of protection of the present invention. In addition, all the connection / connection relations involved in the patent do not only refer to the direct connection of the components, but refer to the fact that a better connection structure can be formed by adding or reducing connection accessories according to specific implementation c...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a drilling and pulling-out method for a foundation pit supporting prestressed anchor cable, and relates to the field of treatment of the prestressed anchor cable of a foundation pit supporting system. The method comprises the following steps of A, construction preparation; B, dismounting of a prestressed anchor cable locking device; C, drilling by a drilling machine; D, first time of cavity filling; E, second time of cavity filling; and G, hole closing. The method has the beneficial effects that the method meets various construction requirements, the anchor cable is pulled out, the surrounding environment is not disturbed, and the pulling-out success rate of the prestressed anchor cable, namely safety of operators is ensured.

Description

Technical field [0001] The invention relates to the field of pre-stressed anchor cable treatment of a foundation pit support system. More specifically, the invention relates to a method for drilling, chiseling and pulling out a pre-stressed anchor cable for foundation pit support. Background technique [0002] Deep foundation pit support usually adopts the form of retaining pile + prestressed anchor cable. After the local lower chamber is backfilled, the prestressed anchor cable of the retaining structure loses its use function but intrudes into the underground space outside the original foundation pit. (Structure) Subsequent excavation and construction of structures will cause impacts. For example, when urban subway tunnels are constructed under the shield tunneling method, or when the surrounding new basement enclosure structure is constructed, the pre-stressed anchor cables in the early construction will cause huge obstacles to the construction. The construction difficulty and...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E02D17/04E02D5/76
CPCE02D5/765E02D17/04
Inventor 洪明坚肖养遴刘晓宁张立学雷斌崔炳辰周明佳
Owner SHENZHEN GEOKEY CONSTR GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products