Sand pile construction method adopting multi-section composite casing punching
A composite casing and multi-stage technology, which is applied in basic structure engineering, soil protection, construction, etc., can solve problems such as difficulty in maintaining the design bearing capacity of sand, loosening and subsidence of surrounding soil, and inability to ensure the quality of piles, so as to reduce residual waste. The amount of soil transported, the effect of ensuring the compactness and ensuring the construction quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0034] The construction method of the multi-stage composite casing stamping sand pile provided in this embodiment includes the following steps:
[0035] (1) The composite casing is in place vertically
[0036] Set out the sand pile position according to the construction layout plan. The hole position and on-site elevation measurement should be carried out in advance to clarify the center of the hole position and the depth of the sand pile. The measuring instruments use a total station and a level. According to the design requirements and soil layer conditions, determine the hole position and make a mark.
[0037] (2) Hammering composite casing
[0038] Put the pile driver in place, close the pile tip of the flap, and vertically lower the pipe pile so that the pile tip is aligned with the pile position mark, and continue to vertically move the pile pipe to make the pile tip into the soil. Start the pile hammer motor to vibrate the pile hammer to make the pile pipe sink to the...
Embodiment 2
[0048] Embodiment 2 application example
[0049] (1) Jiahejiayuan 4#, 5#, 7#, underground garage and network project
[0050] Project Overview
[0051] Jiahejiayuan 4#, 5#, 7#, F area outlets and underground garage project are located in the north of Yingbin Road, Qingyun County, Dezhou City, and west of Kaiyuan Street. , with a total construction area of 54691.06㎡. Because the foundation of the northwest section is silt soil about 4m deep, the foundation construction can only be carried out after the foundation has been treated.
[0052] Construction
[0053] The northwest section of this project adopts the construction technology of multi-stage composite casing stamping sand piles, and a sand pile is set every 2m, and a total of 1312 sand piles are used.
[0054] apply effects
[0055] The construction of the multi-stage composite casing stamping sand pile in this project has been jointly checked and accepted by the design, supervision, supervision, construction and c...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com