Construction method of outdoor water works engineering
A construction method and technology for water supply engineering, applied in water conservancy projects, water supply main pipelines, infrastructure engineering and other directions, can solve the problems of inability to meet the requirements of drinking water quality, unsanitary cast iron water pipes, short service life, etc., and it is not easy to lose. , accurate marking, accurate construction effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0058] The construction method of outdoor water supply works includes the following construction steps:
[0059] 1. Preparation before construction
[0060] 2. Measurement and setting-out
[0061] Before starting construction, organize a skilled and capable surveying team to bury and re-measure the baseline level points, construction guide points and curve elements provided by the design, and establish a plane survey control network. The accuracy must meet the construction survey specifications and design requirements; Coordinate points, benchmark points, and curve element points along the entire line of control points should be checked frequently and protected during the construction process.
[0062] 2.1 Retesting of control points
[0063] After the intersection between the owner and the supervisor, take the plane control point and elevation control point data within the construction range from it, find the position of the control point on the site, and perform repeated r...
Embodiment 2
[0134] The difference between Example 2 and Example 1 in the construction method of the outdoor water supply project is that in S4, cement self-leveling is laid on the surface of the pipeline foundation after the pipeline foundation is tamped, and the water supply pipeline is laid after the cement self-leveling is dried and solidified.
[0135] Cement self-leveling is a high-tech green product with high technological content and complicated technical links. The self-leveling cement applied in the present invention flows automatically after spreading into the groove, and automatically finds low-lying areas on the ground and fills them up. Finally, the whole ground flows into a mirror-like smoothness and then stops, and quickly dries and solidifies. The resulting ground will form a smooth, flat, seamless new base. It is more convenient to lay the water supply pipe after the groove is leveled, especially at the connection of adjacent water supply pipes. It is flat, wear-resistan...
Embodiment 3
[0137] The construction method of the outdoor water supply project, the difference between embodiment 3 and embodiment 1 is that after the water supply pipe is installed in S5, an arc-shaped steel plate is placed on the water supply pipe. The curved steel plate completely wraps the water supply pipe, and both sides extend into the ground.
[0138] The arc-shaped steel plate has relatively high strength and has a good protective effect on the water supply pipe. Especially when backfilling the trench, the impact of sand and stone on the water supply pipe is transformed into the arc-shaped steel plate, and the water supply pipe is not easily damaged. During the construction process, there is no need to be as careful as before, which is conducive to improving construction efficiency.
PUM
Property | Measurement | Unit |
---|---|---|
Thickness | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com