BIM-based water conservancy and hydropower project management cloud platform and application method thereof

A technology of engineering management, water conservancy and hydropower, applied in data processing applications, instruments, calculations, etc., can solve problems such as low collaboration efficiency, information loss, and cross-effects of problems, and achieve the goal of maintaining timeliness, clarity, and integrity Effect

Inactive Publication Date: 2016-10-12
ZHENGZHOU SHUANGJIE TECH CO LTD
View PDF1 Cites 43 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

With the progress of the process, changes in participating units, adjustments in business departments, and transfers of personnel, the traditional paper-based data management model often results in a large loss of information, which brings many problems to the identification of contract responsibilities, handling of claims, and acceptance of project completion. Negative Effects
[0006] 2. Work collaboration management is difficult
Contracts are generally used in domestic engineering construction to constrain all parties involved in the construction, and it is difficult to deal with and control real-time detailed issues that occur in the construction process in real time
Coupled with management expertise and departmental barriers, it often results in low collaboration efficiency, resulting in problems such as cross-influence, cross-interference, and management out of control.
[0008] 3. Lack of real-time analysis and evaluation technology
Obviously, this management method cannot achieve real-time process tracking, dynamic change analysis, and timely control, adjustment, and optimization, which will inevitably lead to the accumulation of problems and impacts, and increase the difficulty of subsequent coordination and processing.
[0010] 4. Lack of effective risk control analysis methods
The traditional construction management method, first, lacks effective information management technology, and there are loopholes in information management; second, it lacks the assessment and analysis technology of the schedule plan, making it difficult to find hidden dangers in the schedule arrangement; third, it cannot analyze the implementation process in real time, which is easy Problems have accumulated; fourth, the contract management work lacks accurate and multi-faceted information support, and the division and identification of responsibilities are unclear, resulting in protracted delays in resolution
Therefore, it is difficult to scientifically and effectively carry out risk control in various aspects such as progress, quality, contracts and claims
[0012] The key to the comprehensive analysis of common problems and phenomena in the field of engineering construction management lies in the lack of advanced management and analysis technology in the face of complex engineering space information and massive business information generated in the engineering construction process, and effective support for decision-making management

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • BIM-based water conservancy and hydropower project management cloud platform and application method thereof
  • BIM-based water conservancy and hydropower project management cloud platform and application method thereof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0047] Embodiment 1: A BIM-based water conservancy and hydropower project management cloud platform, see figure 1 ,include:

[0048] Data acquisition layer, data acquisition layer includes project information management and spatial information measurement, project information management is used to collect project management information, and spatial information measurement is used to collect spatial measurement information. Project information management includes basic data management, engineering budget data, engineering contract data, engineering progress data, engineering quality data, and engineering resettlement data; the spatial information measurement includes terrain data, engineering design data, engineering planning data, and resettlement planning data.

[0049] Communication network layer, the communication network layer includes local area network, VPN private network or public network,

[0050] Data resource layer, the data resource layer includes BIM models, stor...

Embodiment 2

[0054] Embodiment 2: An application method of a BIM-based water conservancy and hydropower project management cloud platform, see figure 2 , including data acquisition, data processing and data application.

[0055] Data collection: including project management information and spatial measurement information collected from the construction site and construction participants. Project management information includes basic management data, project budget data, project contract data, project progress data, project quality data, and project resettlement data, etc. information. Spatial measurement information includes terrain data, engineering design data, engineering planning data, and resettlement planning data. The collected data is reorganized or arranged by the construction participants and sent to the BIM model in the data resource layer through the local area network, VPN private network or public network. Spatial measurement information of hydraulic engineering or other p...

Embodiment 3

[0062] Embodiment 3: Embodiment 3 is basically the same as Embodiment 2, and the similarities will not be repeated. The difference is that the BIM engineering management platform also includes a simulation calculation BIM model, and the establishment of the simulation calculation BIM model includes the following steps:

[0063] (1) Based on the automatic acquisition of monitoring data during the construction period: through various hardware equipment and software analysis systems that meet the real working performance analysis of the dam, and through big data technology, the automatic analysis of massive data can be realized to meet the requirements of numerical simulation;

[0064] (2) Establishment of the numerical simulation model for the whole process of the whole dam: establish a numerical simulation analysis model of the whole process of the whole dam based on the cloud platform architecture, and the simulation model considers the whole process of complex foundation faults...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

A BIM (Building Information Modeling)-based water conservancy and hydropower project management cloud platform comprises a data acquisition layer, a communication network layer, a data resource layer, an application support layer, and a service application layer. The data acquisition layer includes project information management and spatial information measurement; the communication network layer includes a local area network, a VPN (Virtual Private Network) or a public network; the data resource layer includes a BIM model which is stored in a public cloud, in a private cloud or in a hybrid cloud and includes a BIM integrated database; the application support layer includes a BIM project management platform and a data exchange platform; and the service application layer includes BIM information query, construction process BIM management and BIM information output. The BIM integrated database is connected with different project object data, processes and resources, is a digital expression of construction facilities which contains rich data, is object-oriented and has intelligent and parametric characteristics, and supports dynamic information creating, sharing, updating and managing in the life cycle of a project.

Description

technical field [0001] The invention relates to the technical field of water conservancy and hydropower project management, in particular to a BIM-based water conservancy and hydropower project management cloud platform and an application method. Background technique [0002] The construction management of water conservancy and hydropower projects has always been a complex subject, involving the division of labor and strict control among multiple projects, multiple levels, multiple roles and multiple businesses, and the management process is intricate. How to do a good job in project construction planning management, progress control, quality control, contract management, budgetary control and resettlement management is always the core of project construction management. Throughout the construction of domestic water conservancy projects, from construction planning management, construction progress control to resettlement and resettlement management, etc., there are common pr...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q50/08
CPCG06Q50/08
Inventor 魏鲁双
Owner ZHENGZHOU SHUANGJIE TECH CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products