Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Synchronous construction method for TPZ red core molecular level bonding waterproof coiled material

A waterproof membrane and simultaneous construction technology, applied in the direction of polymer adhesive additives, non-polymer adhesive additives, and roofs using flexible materials, etc., can solve the problems of long waterproof construction period, loss of strength, and failure of wet laying and sealing To achieve the effect of saving the direct cost of the project, prolonging the life of the building, and eliminating water leakage

Inactive Publication Date: 2016-09-21
LIAONING DAYU WATERPROOF TECH DEV
View PDF5 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0008] (1) The waterproof safety is poor, and there is a potential risk of leakage
[0009] ① Long-term deposition of silt on the waterproof base surface, concrete or cement mortar dropped and bonded to the base surface, and laitance on the concrete base surface are all very difficult to clean up, and it is difficult to meet the cleanliness requirements of the base layer required for wet-laying coils , resulting in delamination of the cement sealant used for the wet-laid coil material and the base layer after solidification, resulting in the failure of the seal between the wet-laid coil material and the base surface, and the risk of large-scale water leakage in the project
[0010] ②The smooth concrete or cement mortar waterproof base surface after complete curing makes the cement sealant material used for wet-laying coils easy to delaminate with the base layer after solidification, resulting in failure of sealing between wet-laying coils and the base surface, and major engineering accidents Risk of area channeling and water leakage
[0011] ③The base surface of dry concrete or cement mortar is difficult to wet to the saturated state of water content, and the wet-laid coils are paved with cement mortar. Because the cement mortar is very thin (thickness is about 1.5mm), it is easy to absorb water from the base layer. Cause the cement slurry to lose water and lose its strength, cause the wet laying seal to fail, and cause large-scale water leakage
[0012] ④ It is impossible to avoid the engineering leakage caused by forced waterproofing construction when the waterproof base layer cannot meet the waterproof construction conditions due to rushing the construction period and other reasons, resulting in waterproof defects
If the waterproof layer is damaged or defective, the open water infiltrated into the waterproof layer will spread along the mortar leveling layer and the channel between the structural layer and the channel, causing engineering leakage
[0015] (2) The waterproofing construction period is long and cannot cope with projects with a tight construction period
Although this method uses the method of wet laying, the waterproof construction of the coiled material is carried out after the base surface reaches the design strength and is dry, which seriously affects the safety of wet laying and sealing, and large-scale water leakage is prone to occur in waterproofing projects

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Synchronous construction method for TPZ red core molecular level bonding waterproof coiled material
  • Synchronous construction method for TPZ red core molecular level bonding waterproof coiled material
  • Synchronous construction method for TPZ red core molecular level bonding waterproof coiled material

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0080] Simultaneous construction of basement floor waterproofing:

[0081] Such as figure 1 As shown, the synchronous construction of the TPZ red core molecular adhesive waterproofing membrane and the underground engineering floor cushion concrete is a schematic diagram of each layer from top to bottom:

[0082] (1) Concrete protective layer;

[0083] (2) TPZ red core molecular adhesive waterproof membrane layer;

[0084] (3) wet cement mortar layer;

[0085] (4) Concrete cushion.

[0086] The simultaneous construction of the basement floor cushion concrete of the TPZ red core molecular adhesive waterproof membrane includes the following steps:

[0087] (1) For the construction of waterproof base concrete cushion, the surface needs to be leveled and calendered once, and the thickness of the cushion is 100-150mm;

[0088] (2) After 4 hours, when the concrete surface can withstand a pressure above 10KPa, remove the isolation film on the lower surface of the TPZ red core mol...

Embodiment 2

[0097] Simultaneous construction of basement roof waterproofing:

[0098] Such as figure 2 As shown, the synchronous construction of the TPZ red core molecular adhesive waterproofing membrane and the roof structure concrete of the underground project shows the schematic diagrams of each layer from top to bottom:

[0099] (1) Concrete protective layer;

[0100] (2) TPZ red core molecular adhesive waterproof membrane layer;

[0101] (3) wet cement mortar layer;

[0102] (4) Roof structure concrete.

[0103] The simultaneous construction of the underground roof structure concrete of the TPZ red core molecular adhesive waterproof membrane includes the following steps:

[0104] (1) Concrete construction of the basement roof structure, the surface needs to be leveled and calendered once, and the thickness of the roof concrete is 150-400mm;

[0105] (2) After 3 hours, when the concrete surface can withstand a pressure above 10KPa, remove the isolation film on the lower surface ...

Embodiment 3

[0113] Such as image 3 As shown, the synchronous construction of the TPZ red core molecular adhesive waterproof membrane and the roof structure concrete structure schematic diagrams of each layer from top to bottom are:

[0114] (1) Cement mortar protective layer;

[0115] (2) TPZ red core molecular adhesive waterproof membrane layer;

[0116] (3) wet cement mortar layer;

[0117] (4) Roof concrete structure layer.

[0118] The simultaneous construction of the underground roof structure concrete of the TPZ red core molecular adhesive waterproof membrane includes the following steps:

[0119] (1) For the concrete construction of the roof structure, the surface needs to be leveled and calendered once, and the thickness of the roof structure plate is 120-300mm;

[0120] (2) After 3 hours, when the concrete surface can withstand a pressure above 10KPa, remove the isolation film on the lower surface of the TPZ red core molecular sticky waterproof membrane, and use cement morta...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
thicknessaaaaaaaaaa
thicknessaaaaaaaaaa
thicknessaaaaaaaaaa
Login to View More

Abstract

The invention discloses a synchronous construction method for TPZ red core molecular level bonding waterproof coiled material. According to the synchronous construction method, TPZ red core molecular level bonding waterproof coiled material is constructed together with concrete / cement mortar base layer, wherein the method comprises following steps: base layer concrete construction; after 2-4 hours of the concrete construction, waterproof coiled material is wetly paved; after 24-48 hours of the wet paving of the waterproof coiled material, concrete protective layer construction is performed. The synchronous construction method is safer in water resistance, higher in construction efficiency, and simpler in waterproof structure arrangement.

Description

technical field [0001] The invention relates to a waterproof coiled material, in particular to a synchronous construction method of a TPZ red core molecule-adhesive waterproof coiled material. Background technique [0002] At present, the waterproof materials used for buildings, tunnels and garage roofs are mainly various waterproof rolls. Different waterproof membranes have different requirements for the base surface during construction. SBS, self-adhesive and other waterproof membranes, the waterproof construction base surface must be dry, flat, and reach the design strength of the base before construction; traditional wet-laid coils can be constructed on a wet base, but the waterproof base requires complete curing and reaches the design strength. The surface is flat and has strict requirements on the waterproof base. [0003] The following treatment should be carried out on the base layer before the waterproof construction of the wet-laid membrane: [0004] (1) Cleanin...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E04D5/10E04D5/14E02D31/02C09J195/00C09J11/04C09J11/08
CPCE04D5/10C08L2205/02C08L2205/035C09J11/04C09J11/08C09J195/00E02D31/02E04D5/148C08L91/00C08L9/06C08L11/00C08L9/02C08L57/02C08K3/08
Inventor 郑宪明吴敏慧魏利兰
Owner LIAONING DAYU WATERPROOF TECH DEV
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products