Eureka AIR delivers breakthrough ideas for toughest innovation challenges, trusted by R&D personnel around the world.

Installation method of prefabricated platform

An installation method and a technology of prefabricated caps, which are applied in the direction of erecting/assembling bridges, bridges, buildings, etc., can solve problems such as long construction period, and achieve the effects of reducing construction costs, improving stability, and small surface area

Active Publication Date: 2015-08-12
CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
View PDF2 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, in the existing construction methods of bridge caps in China, large-scale steel cofferdams are still mainly cast-in-situ. Although there are also examples of prefabricated installation of caps, most of them are only prefabricated cap shells, and the cap shells are used as cofferdams. Hoisting and lowering, the concrete inside the cap is poured after the cap is lowered into place. For the above-water construction in areas with strong wind and waves, auxiliary steel cofferdams are still required. The entire construction period is longer, and the time for water operations has not been shortened.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Installation method of prefabricated platform
  • Installation method of prefabricated platform
  • Installation method of prefabricated platform

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0026] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0027] see figure 1 , 2 As shown, the embodiment of the present invention provides a method for installing a prefabricated platform, including the following steps:

[0028] A. Complete the prefabrication of caps and bottom pier bodies in the prefabrication plant, reserve holes for pile foundations, steel bar joints, reserved holes for steel rods and pre-buried bolts for fixing steel cylinder cofferdam 1, and wait for the caps to reach the design strength Afterwards, install the steel cylinder cofferdam 1, the steel rod 3 for hoisting the cap, the first pole for hanging piles 4 and the second pole for hanging piles 5, and a steel cylinder cofferdam 1 is set at each pile foundation reserved hole, each Steel cylinder cofferdams 1 are connected by connecting systems to enhance their overall stability; see image 3 As shown, the steel c...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a prefabricated bearing platform mounting method and relates to the field of bridge construction. The prefabricated bearing platform mounting method comprises the following steps that a bearing platform and bottom pier bodies are prefabricated in a prefabrication field, and steel pile hole positions are reserved in the bearing platform; the bearing platform is lifted to a pile site by a large floating crane; a pile top guiding device is pre-mounted on steel piles in the pile site before the bearing platform is lifted; after the bearing platform is lifted down and is in place, a carrying pole is arranged on a pile top longitudinal direction adjusting position in a hanging manner, and the horizontal plane of the bearing platform is regulated as required; and the pouring of bottom-sealing concrete of a steel cylinder cofferdam, the water pumping, the binding of reserved hole steel reinforcing bars, and the pouring of reserved hole concrete at non-lifting points and lifting points are sequentially finished, and the steel cylinder cofferdam is detached, so that the mounting of the prefabricated bearing platform is finished. According to the prefabricated bearing platform mounting method disclosed by the invention, a small steel cylinder cofferdam replaces a large bearing platform steel cofferdam, so that the steel material can be effectively saved, the on-water operation time is shortened, and the construction cost is reduced; and meanwhile, the influence of water flow to the construction of the bearing platform is reduced, and the construction quality of the bearing platform is ensured.

Description

technical field [0001] The invention relates to the field of bridge construction, in particular to a method for installing a prefabricated cap. Background technique [0002] With the development of economy and society, the construction of cross-sea bridges has gradually become the theme of bridge construction. Since the geographical location of the cross-sea bridge has a special marine climate - strong winds, high waves, rapid currents, frequent typhoons and natural disasters, and the cross-sea bridge spans a long distance with a large number of pier caps, in order to overcome this Due to the various adverse effects of marine climate characteristics, when formulating construction plans and measures, the time for water operations should be reduced as much as possible, and water construction should be changed to land construction, forming "large-scale construction equipment, factory-based bridge components, standardized production processes, and bridge construction. The "four...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E01D21/00E02D19/04E02D27/14
Inventor 李军堂叶庆旱马涛涂满明姚发海张瑞霞许佳平姚森王东辉张爱花王艳峰李少一黄剑锋吕磊
Owner CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Eureka Blog
Learn More
PatSnap group products