Method for constructing bearing platform on deepwater and rigid impermeable layer
A technology of permeable layer and construction method, applied in the field of bridge pile foundation construction, can solve problems affecting construction progress and construction quality, and achieve the effect of ensuring construction quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] The invention provides a method for constructing caps on deep water and hard impermeable layers, and uses steel sheet piles and low casings to combine cofferdams for construction. The process is simple, the structure is stable, and an anhydrous construction environment can be provided, thereby ensuring construction quality . The present invention will be described in detail below in conjunction with the accompanying drawings.
[0032] The method for constructing caps on deep water and hard impermeable layers provided by the invention comprises the following steps:
[0033] Step 1. Before the construction of the cap, choose the low water level to build an artificial island 11 or build a construction platform at the design position of the cap, and complete the construction of the foundation bored pile 10 .
[0034] At the same time as the construction of the foundation bored pile 10, the four corners of the artificial island 11 or the construction platform (within the ra...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com