Construction method for continuously laying structural layers of highway pavement

A construction method and technology of pavement structure, which can be applied to the coagulation pavement, roads, roads and other directions of on-site paving, can solve the problems affecting interlayer bonding, interlayer pollution, long construction period, etc. Continuity, the effect of shortening the health period

Inactive Publication Date: 2012-06-20
江苏省淮安市公路管理处
View PDF2 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0008] "Technical Specifications for Construction of Highway Pavement Base Course" (JTJ034-2000) specifies the construction procedures for pavement subbase, base course, and surface course as follows: subbase paving construction——covering and moisturizing——basic paving construction——covering and moisturizing— — Surface layer paving construction; the construction period of this traditional technological process and health preservation is relatively long. The discontinuous construction between layers is likely to cause interlayer pollution or surface layer damage and affect the interlayer bonding. Covering layer by layer to moisturize and maintain health is not only a process Many and high cost; at present, with the continuous improvement of road mechanized construction level and modern construction management level, the quality assurance rate of road engineering construction is more stable, therefore, it is necessary to explore and innovate traditional construction methods

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0018] Example: Continuous and rapid construction of highway subgrade and pavement according to the following steps

[0019] 1. On the top surface of the filled subgrade that has been constructed and passed the inspection and acceptance, the paving construction of the sub-base of the pavement shall be carried out continuously;

[0020] 2. In accordance with the relevant specifications and standards, the raw materials, mixtures, external dimensions, quality control, etc. of the sub-base shall be inspected and accepted for the quality of the project (the strength index is postponed until the asphalt concrete surface layer is laid and the overall natural health is completed. checking);

[0021] 3. Then the paving construction of the pavement base is carried out continuously;

[0022] 4. Carry out engineering quality inspection on the raw materials, mixtures, external dimensions, and quality control of the base in accordance with relevant specifications and standards and pas...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method for continuously laying structural layers of a highway pavement. The construction method comprises the following steps of: filling an earth-filled road foundation by layers, compacting by layers to finish all the constructions, carrying out quality test to be qualified, and continuously carrying out paving construction on a pavement underlayer; after all the constructions of the pavement underlayer are finished, carrying out quality test to be qualified, and continuously carrying out paving construction on a pavement base layer; after the all the constructions of the pavement base layer are finished, carrying out quality test to be qualified, continuously carrying out paving construction on a pavement surface layer; and finally, after all the constructions of the pavement surface layer are finished, strictly closing traffic, forming integral covering, heating and maintaining on the base layer and underlayer by naturally absorbing solar energy with black bituminous concrete of the surface layer, synchronously finishing safety construction, and opening traffic for use. According to the invention, integral maintaining is carried out after continuously laying and forming, thus the maintaining and forming of the underlayer and the base layer of the pavement are favorably accelerated, the construction times of the underlayer and the base layer of the pavement are effectively shortened, the construction working efficiency is increased, the construction cost is lowered and the maintaining cost is reduced.

Description

technical field [0001] The invention belongs to the technical field of highway traffic infrastructure construction, and in particular relates to a construction method for continuous paving of highway pavement structural layers, that is, a construction method in which the highway pavement structural layers are first continuously paved and formed, and then the whole is naturally preserved. Background technique [0002] As we all know, to build a highway, the construction period is generally 3 years. In addition to the preliminary work of related projects such as survey and design, land acquisition and demolition, the construction period will take at least 18-24 months. Usually, the construction starts from the original ground, and goes through the process of measuring and setting out, filling the subgrade, laying the road, installing safety facilities, and planting greening. [0003] Filled roadbed is composed of pre-filling treatment layer and multi-layer filling layer. The c...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E01C7/32E01C3/04
Inventor 张玉恒
Owner 江苏省淮安市公路管理处
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products