Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam

A concrete box girder, segmental prefabrication technology, applied in bridges, bridge materials, bridge construction, etc., can solve problems such as cracks, achieve the effect of eliminating cracks and preventing cracks itself

Active Publication Date: 2011-03-16
HUNAN ROAD & BRIDGE CONSTR GROUP
View PDF2 Cites 23 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The purpose of the present invention is to provide a construction method of high-altitude segmental prefabrication, beam moving, beam storage, and assembly of large concrete box girders, so as to solve the problems caused by the shrinkage and creep of the beam body and the settlement of the support during the construction process of the overly long beam section. The problem of cracks caused by deformation

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam
  • Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam
  • Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0031] The inventive method comprises the following steps, see Figure 1 to Figure 9 :

[0032] 1. Set up a high-pile prefabricated platform 1 on the shore side (shore side) of the bridge. The high-pile prefabricated platform 1 adopts a steel pipe support structure, and arranges the formwork system required for the prefabricated beam section. See figure 1 , figure 2 ;

[0033] 2. Along the bridge direction, set up a beam-moving steel pipe support 2 between the high pile prefabricated platform 1 and the pier column 13 on the river side (river side) of the bridge. The beam-moving steel pipe support 2 is a load-bearing structure for the movement and storage of the beam section; Two parallel steel slide rails 5 are set on the beam-moving steel pipe support 2; Set cross braces and scissors braces to ensure the overall stability of the support; install distribution steel beams 6 in the cross bridge direction on the beam-moving steel pipe support 2, as the support of the load-bea...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of a large concrete box beam, which is characterized by comprising the following steps: 1) erecting a high-pile prefabricated platform; 2) erecting beam moving steel tube supports and steel slide rails between the high-pile prefabricated platform and a pier; 3) pouring a matched beam section on the high-pile prefabricated platform; 4) using the poured matched beam section as the end die at one end of the next new beam section to be poured and pouring the new beam section; 5) after pouring the new beam section, transporting the matched beam section to the design position as the beam section to be assembled and simultaneously moving the new beam section forward as the next matched beam section; 6) longitudinally moving the beam section to be assembled to the matching surface of the end of the assembled beam section as the beam section to be assembled and adjusting the position of the beam section to be assembled to ensure the beam section to be assembled to conform to the requirement of split joint with the assembled beam section on the pier; and 7) carrying out split joint on the beam section to be assembled and the assembled beam section. By section prefabricating and long-time beam storing of the beam sections, the construction method effectively ensures the prefabricated beam sections to complete most contraction deformation of the beam body in free state and eliminates the contraction difference of the adjacent beam sections caused by different ages, thus eliminating cracks.

Description

technical field [0001] The invention belongs to bridge construction methods, and in particular relates to a construction method of high-altitude segmental prefabrication, beam moving, beam storage and assembly of large concrete box girders. Background technique [0002] At present, domestic and international construction of large concrete box girders generally adopts segmental cast-in-place construction. However, during the construction process, due to the restriction of the shrinkage of the concrete poured in the previous segment on the shrinkage of the concrete poured in the latter segment, poor concrete shrinkage occurs, resulting in cracks. At the same time, since the concrete pouring is mostly divided into sections according to the entire span, the volume of a single-section beam is too large, so that the beam section is prone to free shrinkage cracks due to its own constraints. [0003] In China, most bridges of this type require continuous pouring across the entire sp...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E01D21/00E01D101/24E01D2/04
Inventor 欧阳钢陈明宪肖跃文方联民丁望星林立军刘武
Owner HUNAN ROAD & BRIDGE CONSTR GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products