Tubular microporous tailing damming method
A technology of tailings and micropores, which is applied in the direction of filling, etc., can solve the problems of dry beach length and safety superhigh that are difficult to meet the requirements, many safety hazards, and unfavorable environmental protection, etc., to achieve good drainage effect, safe superhigh, and separation good sex effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0021] A method for building a tubular microporous tailings dam, comprising the following steps:
[0022] (1) Make the ore drawing pipe 3: the ore drawing pipe 3 adopts a medium and small diameter pipe, and the ore drawing holes 6 that are evenly arranged are drilled intermittently in the opposite direction under the ore drawing pipe 3;
[0023] (2) Install the ore-drawing pipe support 4: the ore-drawing pipe support 4 is arranged on the dry beach 5 in the storehouse, and the ore-drawing pipe support 4 is installed and fixed on the dry beach 5 in the storehouse with a set distance from the top of the sub-dam 2;
[0024] (3) Install the ore-drawing pipe 3: install and fix the prepared ore-drawing pipe 3 on the ore-drawing pipe support 4;
[0025] (4) Adjust the ore-drawing hole 6: open and block the ore-drawing hole 6 as required during ore drawing;
[0026] (5) Dam building: while the ore is drawn, the tailings are deposited into a sub-dam 2 with higher strength connected to ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com