Watersaving construction technique for maintaining concrete wet
A construction technology and concrete technology, applied in the direction of roads, road repair, roads, etc., can solve the problems of unsatisfactory water conservation and maintenance time, affecting the service life of concrete, etc., and achieve the effect of reducing maintenance construction costs and improving maintenance quality.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0030] Embodiment 1: The semi-rigid base of the expressway, 4% cement stabilized crushed stone, the width of the roadbed is 13.23 meters, and the thickness is 36 centimeters. The maintenance adopts the 102 products of Yanghushen-1 series. After the concrete roadbed is paved, lay 15 rolls of curing film core film on the roadbed one by one or at the same time. The core membrane absorbs 0.8 kg of water. Then cover the mask on the core film (9.4×13.8m 2 ), press both sides with heavy objects to prevent the wind from blowing up. There is no need to water again during the curing period.
Embodiment 2
[0031] Embodiment 2: No. 325 cement concrete pavement, the pavement width is 8.25 meters, and the thickness is 26 centimeters. The maintenance adopts 102 products of the Yangyang-1 series. After the concrete pavement is paved and the expansion joints are cut, lay 10 rolls of curing film core film on the road surface one by one or at the same time. The laying direction is parallel to the road surface direction, and then sprinkle water evenly on the core film until the core film fully absorbs water and bulges up evenly. At this time, the core membrane absorbs 0.8 kg of water per square meter. Then cover the mask on the core film (50×9.5m 2 ), press both sides with heavy objects to prevent the wind from blowing up. There is no need to water again during the curing period.
Embodiment 3
[0032] Example 3: The cement concrete pavement of the airport runway is 48m wide. It is divided into 12 layings. The width of each laying is 4m and the thickness is 25cm. After the airport concrete pavement is paved and the expansion joints are cut, the curing film core is laid on the pavement in sequence, the laying direction is perpendicular to the pavement direction, and then water is evenly sprinkled on the core film, and the core film absorbs 0.8 kg per square meter until the core film fully absorbs water and bulges up evenly, then cover the core film with a mask (15×5.0m 2 ), both sides are pressed with sand and gravel to prevent the wind from blowing up. There is no need to water again during the seven-day maintenance period.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com