Tunnel secondary lining construction process
A secondary lining and construction technology technology, applied in the direction of tunnel lining, tunnel, shaft lining, etc., can solve the problems of layer jump pouring, concentrated material distribution, delay in taking over, etc., to achieve the effect of avoiding centralized material distribution, saving construction costs and avoiding omissions
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0040] The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
[0041] see Figure 1-4 As shown, a tunnel secondary lining construction process includes the following steps S1-S4.
[0042] S1. According to the tunnel design data, make a two-lined formwork trolley. The two-liner formwork trolley includes a forming formwork part and a pouring part.
[0043] From bottom to top, the two side wall sections of the forming template part are sequentially provided with multiple first-level working window...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com