Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

A section design method of deep buried pba subway station

A section design, subway station technology, applied to mining equipment, earthwork drilling, underground chambers, etc., can solve the problems of reducing land subsidence, complex surrounding environment, difficult to ensure safety, etc., to reduce the impact of noise and vibration, Good construction environment and guaranteed quality control

Active Publication Date: 2021-01-26
BEIJING NO 4 MUNICIPAL CONSTR ENG +1
View PDF9 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, these methods have different defects and limitations for construction environments with complex surrounding environments, dense underground pipelines, poor geological conditions, abundant groundwater, and large cross-sectional spans.
[0003] 1. For the working conditions with a lot of ground traffic and underground pipelines, the open-cut method must carry out pipeline relocation and traffic evacuation during construction, so the construction is disturbed and the construction period is long; in addition, the temporary relocation of pipelines and the cost of land occupation high, poor economy
[0004] 2. The shallow-buried double-side-wall pilot pit method adopted is extremely unfavorable for the safety control of the pipeline above the structure and the surrounding environment for the construction environment with poor geological conditions, complex surrounding environment, and many underground pipelines, and the construction risk is high. It is difficult to guarantee safety from theoretical analysis
[0006] However, due to its wide application range, the PBA method is suitable for excavation of tunnels with poor strata, poor geological conditions, large spans, and strict ground subsidence requirements, and can reduce ground subsidence and remove temporary support with relatively small workload, simplifying The construction technology and work efficiency are relatively high, so it is applied in the construction of long-span subway stations, but it has not been applied to the construction of deep-buried tunnels
Moreover, it increases the floor area required for construction, increases the workload of demolition and modification and the initial investment, and at the same time brings many uncertain factors in the construction period.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A section design method of deep buried pba subway station
  • A section design method of deep buried pba subway station

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0038] see figure 1 , the construction of a subway station in the central area of ​​a certain northern city. The construction of the subway station runs through the existing city center bridge, and the subway station is symmetrically located on both sides of the bridge. The bridge is equipped with prefabricated concrete retaining walls on both sides of the high fill of the road. Those with a fill height of less than 3m are cantilevered; Set up a settlement joint (expansion joint) at intervals of 2-28m (at the junction of the foundation staggered abutment and the retaining wall and the abutment), the width of the joint is 2cm, and the joint is filled with asphalt and hemp. Linoleum waterproof layer, foundation, ground burden, anti-collision guardrail expansion joints and settlement joints are all consistent with the board joints; the distance between the drain holes is 4m, and they are located at the board joints, and the drain holes are 30cm above the ground line and adopt ga...

Embodiment 2

[0058] A method for designing a section of a subway station using a deeply buried PBA, comprising the following steps:

[0059] a. Detect the ground cavity above the section structure of the station;

[0060] b. Arrange ground dewatering wells and horizontal wells in the cave, and set composite anchor piles 14 on the ground;

[0061] c. Build a large pipe shed 4 at the position above the main arch 1 and the small pilot holes 2 and 3, and carry out deep hole grouting to reinforce the soil;

[0062] d. Construct small pilot tunnels 2 and 3 and pre-embed connecting steel bars;

[0063] e. Erect the grid arches of the small pilot holes 2 and 3, and connect them with the pre-embedded connecting steel bars;

[0064] f. Perform initial support in the small pilot holes 2 and 3, and then install side piles 5 and 6 in the small pilot holes 2 and 3 respectively. Concrete backfill, and then form the crown beams 7 and 8 of the side piles 5 and 6 respectively;

[0065] g. Starting from ...

Embodiment 3

[0086] A method for designing a section of a subway station using a deeply buried PBA, comprising the following steps:

[0087] a. Detect the ground cavity above the section structure of the station;

[0088] b. Arrange ground dewatering wells and horizontal wells in the cave, and set composite anchor piles 14 on the ground;

[0089] c. Build a large pipe shed 4 at the position above the main arch 1 and the small pilot holes 2 and 3, and carry out deep hole grouting to reinforce the soil;

[0090] d. Construct small pilot tunnels 2 and 3 and pre-embed connecting steel bars;

[0091] e. Erect the grid arches of the small pilot holes 2 and 3, and connect them with the pre-embedded connecting steel bars;

[0092] f. Perform initial support in the small pilot holes 2 and 3, and then install side piles 5 and 6 in the small pilot holes 2 and 3 respectively. Concrete backfill, and then form the crown beams 7 and 8 of the side piles 5 and 6 respectively;

[0093] g. Starting from ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

A method for designing a section of a deep-buried PBA subway station, comprising the following steps: a. detecting the cavity; b. laying a composite anchor pile (14) on the ground; c. constructing a large pipe shed (4); d. constructing a small guide hole (2,3); e. erect the grid arch frame of the small pilot hole (2,3); f. carry out the initial support in the small pilot hole (2,3), and then in the small pilot hole (2,3) Construction of side piles (5, 6) respectively; g. Excavation of the main body arch (1), primary support, and concrete pouring of the second lining structure (9); h. Excavation of the lower main body center (10) soil; i. The construction of the bottom plate (11), side wall (12) and middle plate (13) of the lower second lining structure of the lower main body center (10); j. construction of auxiliary structures to form a complete station structure. The method can ensure construction safety, quality and construction period, and can save costs and improve work efficiency; and the section structure design is reasonable, the overall structure is stable, and the construction is simple and the use effect is good.

Description

technical field [0001] The invention belongs to the rail transit equipment industry, and relates to the technical field of underground structure engineering construction of urban rail transit vehicles, in particular to a method for designing a section of a deep-buried PBA subway station. Background technique [0002] At present, the construction technology level of large-span tunnels in China mainly includes open-cut method and shallow buried method. Among them, the shallow burial and underground excavation methods include the double-side wall pilot pit method and the "PBA" method used in large-span subway stations. However, these methods have different defects and limitations for construction environments with complex surrounding environments, dense underground pipelines, poor geological conditions, abundant groundwater, and large cross-sectional spans. [0003] 1. For the working conditions with a lot of ground traffic and underground pipelines, the open-cut method must c...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D9/14E21D9/00E21D11/15E21D11/18E21D11/10
CPCE21D9/00E21D9/001E21D9/003E21D9/14E21D11/10E21D11/15E21D11/18
Inventor 孔恒迟子利岳爱敏彭明玉史磊磊鲍宇姜兆丰戴建伟周健
Owner BEIJING NO 4 MUNICIPAL CONSTR ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products