Spiral soil-squeezing pile hole drilling tool and construction method of cast-in-place pile
A construction method and technology for extruding soil piles, which are used in earth-moving drilling, drill pipes, drill pipes, etc., can solve the problems of difficult to remove virtual soil and slag, and the slag soil is easy to fall to the bottom of the pile, so as to achieve high overall structural strength. , The molding speed is fast, and the effect of ensuring continuity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0033] Such as figure 1 As shown, the present embodiment introduces a screw soil squeezing pile hole drilling tool, which includes a rotating connecting rod 2 and an auger rod 1. Driven by the driving part of the power head, the helical drill pipe 1 is detachably connected under the rotating connecting rod 2, and the axis of the rotating connecting rod 2 and the drilling pipe 1 is provided with a pouring channel 3, and the pouring channel 3 runs through the rotating connecting rod 2, and the pouring channel 3 communicates with the lowermost end of the drill pipe 1. As the connecting rod 2 is rotated to drive the drill pipe 1 to rotate, then the drill pipe 1 can be gradually moved down to perform the operation of drilling the pile hole on the ground. After the pile hole is drilled, the pouring channel 3 is used to directly pour concrete into the pile hole, and Lift the drill pipe 1 upward to ensure the internal and external pressure of the pile hole, reduce the possibility of ...
Embodiment 2
[0040] A construction method for cast-in-situ piles, comprising the following steps:
[0041] S1. Use a long-screw auger to drill holes on the ground. The drilling tools used in the long-screw auger are as in Embodiment 1.
[0042] S2. Rotate the drilling tool in the forward direction, and move the drilling tool downward, and use the auger drill rod 1 to form the pile hole at one time.
[0043] After adopting this step, the pile hole is formed by one-time drilling, and the drill pipe 1 will not be repeatedly lifted out and inserted into the pile hole. In this way, the pile hole is relatively continuous during the formation of the pile hole, and it is not easy to be damaged due to bumps and other reasons. There are more virtual soil and waste residue, and because the drill pipe 1 is an auger drill pipe, most of the soil will be squeezed out of the pile hole through the thread groove formed by the thread, and the remaining soil will be compacted in the thread groove, which is re...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com