Static piling method using jet grouting pile for disturbing hardpan under limited clearance conditions at tidal waters

A technology of hard ground and rotary grouting piles, which is applied to sheet pile walls, buildings, foundation structure engineering, etc., and can solve problems such as inability to construct and limited clearance at the lower part

Inactive Publication Date: 2019-01-01
GUANGZHOU HENGSHENG CONSTR ENG
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] Based on the deficiencies of the prior art, the technical problem to be solved by the present invention is to provide a static pile planting method for rotary grouting piles disturbing hard stratum under the condition of limited clearance in tidal waters. Pile cofferdams are difficult to construct when encountering obstacles such as bridges, the lower clearance is limited, and there are unfavorable conditions such as underlying hard sand layers under the river bed

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Static piling method using jet grouting pile for disturbing hardpan under limited clearance conditions at tidal waters
  • Static piling method using jet grouting pile for disturbing hardpan under limited clearance conditions at tidal waters
  • Static piling method using jet grouting pile for disturbing hardpan under limited clearance conditions at tidal waters

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0037] The embodiment of the present invention is "Datansha Sewage Treatment System Piping Network - Main Stream of Shijing River (Shijing River, Xinshichong) Intercepting Ditch Box (Shijing River Section) Project", which is located along the main stream of Shijing River, Baiyun District, Guangzhou City. For Shijing Street, Tongdewei Street, and Songzhou Street, a 20km-long culvert will be built under the riverbed along the bank. , both sides of Tanchong and the south side road of Ring Expressway, Zhangcunyong construction DN3000 sewage interception pipeline and BXH=4.0×3.0~6.0×3.0, 1.5×2.0 sewage interception box, the total length of sewage interception pipeline is about 20.2km, Shijing The basin of the main river is about 54.3km 2 , the catchment area of ​​the sewage interception pipes and channels is 34.3km 2 , is implemented in four sections, namely the west bank of the lower reaches of the Ishii River (PXA section), the east bank of the lower reaches of the Ishii River (...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a static piling method using a jet grouting pile for disturbing a hardpan under limited clearance conditions at tidal waters. The static piling method comprises the steps of filling of clay cofferdams at the bottom of a bridge for providing a construction platform; protection of an original bridge pier; reverse excavation of a trench in the construction platform; construction of steel sheet pile cofferdams; support in a channel box and construction of earth excavation; backfill of a foundation pit and removal of circuit purlin; and removal of steel sheet piles. According to the static piling method, the steel sheet pile cofferdams are constructed under the limited clearance conditions at tidal influence waters; firstly, the clay cofferdams are filled for providing the construction platform; then, the trench is reversely excavated in a soil construction platform, and a static piling machine is placed in the trench for static pressure piling construction of the steel sheet piles; and the problem of inadequate clearance for construction of the steel sheet piles is solved, and the water tightness and integrality of the steel sheet piles are ensured. When the problem that a substratum is a hard sand layer and consequently the steel sheet piles can not be driven in position occurs during static piling construction of the steel sheet piles, with the method thathigh-quality mud is sprayed under high pressure through the jet grouting pile for loosening a soil layer, the piling resistance is reduced, so that the steel sheet piles are driven to the designed elevation successfully.

Description

technical field [0001] The invention relates to the technical field of municipal engineering, in particular to a method for statically planting piles in hard stratums disturbed by rotary spraying piles under the condition of limited clearance in tidal waters. Background technique [0002] With the large-scale construction of the urban sewage pipe network system, in order to save land and alleviate the problems of land acquisition and demolition, more and more drainage structures are built under the existing riverbed. ——Shijing River Main Stream (Shijing River, Xinshichong) Sewer Interception Ditch Box (Shijing River Section) Project” requires building a 20km-long culvert under the riverbed near the bank, and the foundation pit support of the sewage interception ditch box basically adopts Steel sheet pile support, but the main stream of Shijing River (Shijing River, Xinshiyong) passes through three bridges, and there are other unfavorable factors. For example, when passing th...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D19/04E02D7/20
CPCE02D19/04E02D7/20
Inventor 李慧莹李传辉张连录陈卫文赵强罗宏亮王忠文贺海东冯德成
Owner GUANGZHOU HENGSHENG CONSTR ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products