A simultaneous cable-girder construction method for a cable-stayed bridge with sparse cables

A technology of simultaneous construction and stay cables, applied in cable-stayed bridges, bridges, bridge materials, etc., can solve the problems of large girder stress variation, multi-girder construction period, steel strand damage, etc. Improve construction efficiency and save construction period

Active Publication Date: 2018-03-30
CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
View PDF4 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] In the method (1), the steel strands are stretched one by one, because the steel strands in a single stay cable are large in size, so the steel strands are stretched one by one, which will inevitably occupy too much construction period of the main girder. , and when tensioning one strand at a time, the stress of the main girder changes too much; the steel strand tensioning method in method (2) can save the construction period, but requires large-tonnage group anchor tensioning jacks. It is extremely difficult to construct, and the working clips are likely to cause great damage to the steel strand when the tension is carried out in stages at the same time.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A simultaneous cable-girder construction method for a cable-stayed bridge with sparse cables
  • A simultaneous cable-girder construction method for a cable-stayed bridge with sparse cables
  • A simultaneous cable-girder construction method for a cable-stayed bridge with sparse cables

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0031] The present invention will be described in further detail below in conjunction with the accompanying drawings.

[0032] The invention provides a cable-girder synchronous construction method for a cable-stayed bridge with sparse cables. The cable-stayed bridge with sparse cables includes a main tower 1, a main beam and a plurality of cable-stayed cables 4, and the main beam includes a plurality of alternately arranged cable joints. Section 2 and a plurality of cable-free segments 8, the cable segment 2 and the cable-free segment 8 are concrete box girders, and a stay cable 4 is arranged on the cable segment 2. After the construction of the main tower 1 is completed, Carry out the construction of cable-stayed cable 4 and main girder, the cable-girder synchronous construction method of this cable-stayed cable-stayed bridge comprises the following steps:

[0033] Step 1: See figure 1 , 2 As shown in , 3, the vertical formwork of the first cable segment 2 adjacent to the m...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a synchronous construction method for a sparse-cable-stayed bridge cable beam, and relates to the field of cable-stayed bridge construction. A sparse-cable-stayed bridge to be constructed comprises a main tower, a main beam body and a plurality of stayed cables. The method comprises the following steps: firstly, constructing cabled segments, moving hanging baskets forward after construction of the cabled segments, and tensioning a part of steel strands in the stayed cables of the cabled segments; secondly, constructing cableless segments, tensioning the remaining part of the steel strands in the stayed cables of the cabled segments after completing construction of the cableless segments, and then moving the hanging baskets; thirdly, circulating the construction steps till completing construction of the main beam body. The method can save the construction period, and the steel strands cannot be damaged easily.

Description

technical field [0001] The invention relates to the construction field of cable-stayed bridges, in particular to a cable-girder synchronous construction method for cable-stayed bridges with sparse cables. Background technique [0002] The cable-stayed bridge with sparse cable system is generally designed as a single cable plane, and parallel steel strand cable-stayed cables are used. The main girder is composed of segmental prestressed concrete box. , a single cable-stayed cable contains multiple steel strands and its volume is very large. If the whole cable is used for tensioning, it is necessary to develop a large-tonnage tensioning jack to tension the cable-stayed cable. The main girder of this type of cable-stayed bridge The conventional construction generally adopts the ordinary hanging basket method cantilever pouring construction method, and the construction process is "construction with cable segments → cable-stayed cable threading and tensioning for cable segments →...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E01D21/00E01D11/04E01D101/28
CPCE01D11/04E01D21/00E01D2101/28
Inventor 李成全黄辉曾海平潘东发毛伟琦姜鹏邱攀肖伟涂满明覃勇刚陈开桥
Owner CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products