Eureka AIR delivers breakthrough ideas for toughest innovation challenges, trusted by R&D personnel around the world.

Water blocking type kerb and construction method thereof

A construction method and curb technology, applied in the direction of gutters/curbs, climate change adaptation, etc., can solve the problems of stormwater road damage, stormwater traffic accidents, high reconstruction costs, etc., to achieve improved efficiency, fast installation speed, and economical High benefit effect

Inactive Publication Date: 2015-12-16
JINAN URBAN CONSTR GRP
View PDF7 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The existing drainage methods have at least the following defects: (1) In order to ensure the flatness and strength of the road surface, viaduct, and viaduct as much as possible, the number of gullies must be as small as possible, that is, the distance between adjacent gullies should be set relatively large, generally 30 -50 meters, therefore, in the process of collecting runoff from the bottom surface, the accumulated water on the road will collect fallen leaves, and the accumulated water on the road needs to flow a long distance along the length of the road surface to reach the rainwater outlet. During the flow process, the fallen leaves will accumulate more The more the fallen leaves are, the more the fallen leaves will overlap and increase. When they flow to the rainwater outlet, the accumulated large amount of fallen leaves will often paste the grate of the rainwater outlet, blocking or reducing drainage; (2) most of the current grates are made of metal. Once the grate is stolen, the exposed rainwater outlet is likely to cause traffic accidents; (3) In order to play a drainage role, the rainwater outlet is generally set lower than the road surface. When the vehicle passes through the rainwater that suddenly subsides When the gully is opened, it will inevitably generate a certain impulse. After a certain period of time, the impulse will inevitably cause damage to the road along the gully, which will easily cause damage to the road surface; (4) the size of the existing road gully is mostly 670×370mm, and the grate hole The interval is 2.6mm. When the road surface water reaches 10cm, the gully grate only collects water in the first two rows of grate holes, and the rest of the grate holes do not play any role.
[0004] In order to improve the above-mentioned traditional drainage methods, many cities in my country entered the national sponge city construction pilot scope in 2015, and infiltration facilities need to be built or rebuilt on sidewalks and green spaces. Many of the green flower beds outside the sidewalks and the high-level flower beds in building communities are higher than the ground or Terrain modeling has been carried out, and some slopes have been greened. If it is to be transformed into a sunken green space, the cost of reconstruction will be high, and the gain outweighs the gain

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Water blocking type kerb and construction method thereof
  • Water blocking type kerb and construction method thereof
  • Water blocking type kerb and construction method thereof

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0038] Example 1: Construction process

[0039] (1) The construction process of water-blocking curbs on slope green space is as follows:

[0040] Survey → foundation construction → water blocking curb installation → filter layer construction → back concrete construction and backfill → sidewalk (or roadway) construction → water blocking hole blocking → graded gravel side ditch → sidewalk (or non- Motorway) construction.

[0041] (2) The construction process of high flowerbed water blocking curbs on both sides of the road is as follows:

[0042] Survey → foundation construction → water blocking curb installation → filter layer construction → back concrete construction and backfill → sidewalk (or roadway) construction → water blocking curb water blocking hole blocking → overflow well construction → sidewalk Or non-motor vehicle lane construction.

[0043] (3) The construction process of high flowerbed water-blocking curbs in the building community is as follows:

[0044] Survey → foundati...

Embodiment 2

[0045] Example 2: Specific process flow

[0046] (1) Measuring and setting out

[0047] The surveyor calculates the coordinates and elevation of the curb stone according to the construction drawings, and installs the control piles of the curb stone. The pile distance in the straight section should be 10-15m; the pile distance in the curved section should be 5-10m; the pile distance at the intersection should be 1-5m . The topography and topography should be combined when laying curbs.

[0048] (2) Curb foundation construction

[0049] The curb foundation should be rammed with 12% lime soil or C 15 Concrete foundation; lime soil thickness should not be less than 15cm, C 15 The thickness of the concrete foundation should not be less than 10cm; if the foundation is collapsible, the thickness of lime soil should not be less than 30cm.

[0050] (3) Water blocking curb installation

[0051] Installation sequence: install in sections according to intersections and flower beds, from the middle...

Embodiment 3

[0071] Example 3: Sidewalk (non-motor vehicle lane) construction

[0072] (1) In order to avoid water seepage on the sidewalk (non-motorized vehicle road), the construction shall be carried out after the water blocking curb is completed.

[0073] (2) The raw materials of permeable pavement can only be used after passing the test.

[0074] (3) Permeable pavement engineering must first construct the test section, and summarize the mix ratio and construction parameters. After meeting the design and specification requirements, construct the final mix ratio and construction parameters.

[0075] (4) The construction of permeable cement concrete pavement shall comply with CJJ1 and CJJ / T135 of "Code for Construction and Quality Acceptance of Urban Roads" and CJJ / T135 of "Technical Regulations for Permeable Cement Concrete Pavements", as well as the following requirements: Water permeability coefficient should be 0.5-1. ; The continuous porosity should not be less than 15%.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the field of road infrastructures, and particularly discloses water blocking type kerb and a construction method for the kerb. The water blocking type kerb comprises cuboid stone and is characterized in that symmetric reverse rabbets are formed in the two ends of the cuboid stone, and two pieces of cuboid stone are connected and assembled; the reverse rabbets are connected to form a water blocking hole. The water blocking type kerb is simple in structure, reasonable in design, convenient to use, high in mounting speed, and suitable for high-position flower beds and slope greening in the sponge city construction, facilitates manual carrying, effectively improves the effect and saves the construction cost.

Description

(1) Technical field [0001] The invention relates to the field of road infrastructure, in particular to a water blocking curb and a construction method thereof. (2) Background technology [0002] Road drainage is closely related to everyone, and it is another distinctive feature of an international metropolis. Untimely drainage and incorrect selection of drainage methods will cause unnecessary trouble to the society and the people. Such as walking wet trouser legs, driving mud splashing and so on. [0003] The existing drainage method is to drain the accumulated water of road runoff along the curb from the road radially and collect it at the gully, and lead it into the sewer through the gully to achieve the purpose of drainage. The radial direction refers to the direction perpendicular to the length of the road. The existing drainage methods have at least the following defects: (1) In order to ensure the smoothness and strength of the road surface, viaducts, and elevated roads as m...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01C11/22
CPCY02A30/60
Inventor 王继东孙杰潘云袁大庆高瑞刘锋
Owner JINAN URBAN CONSTR GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Eureka Blog
Learn More
PatSnap group products