Coal mining method for co-mining gas in mine
A coal mining method and gas technology, which are applied in ground mining, mining equipment, earthwork drilling, etc., can solve the problems of destroying the ecological environment, climate warming, low utilization rate, etc. Destruction, the effect of prolonging the service life
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0022] Embodiment one, figure 1 image 3 As shown in Fig. 4, Fig. 5 and Fig. 6, when there is no outburst danger in the coal seam through outburst hazard identification, the steps of coal seam gas co-mining coal mining method are as follows:
[0023] a, first excavate the uphill roadway 5, after the excavation is completed, excavate two transport roadways 9 from the uphill roadway 5 to both sides of the mining face 15;
[0024] b. Excavate the air-conditioning roadway 8 near and parallel to the uphill roadway 5, and then excavate the section return air level roadway 14 and the section transportation level roadway 7 on both sides of the air-conditioning roadway 8, and finally excavate the working face cut eye 12, complete Overall roadway excavation works;
[0025] C, install the air-conditioning system 11 that is made of ventilator 16, air-conditioner 18 and dust removal equipment 17 inside air-conditioning roadway 8;
[0026] d. Install two airtight doors 1 that can pass mi...
Embodiment 2
[0033] Embodiment two, figure 2 image 3 As shown in Fig. 5 and Fig. 6, when the coal seam is identified as outburst risk by the outburst risk, the steps of the coal gas co-mining coal mining method for the outburst dangerous coal seam are as follows:
[0034] a. After the tunneling of the uphill roadway 5 and the return airway 6 is completed, two transport roadways 9 are excavated from the uphill roadway 5 to both sides of the mining face 15 respectively; Two arc-shaped pressure-relieving tunnels 10 connected to the section return air tunnel 14 and the section transportation tunnel 7 respectively to reduce wind flow resistance;
[0035] b. Excavate the air-conditioning roadway 8 near and parallel to the uphill roadway 5, and then excavate the section return air level roadway 14 and the section transportation level roadway 7 on both sides of the air-conditioning roadway 8, and finally excavate the working face cut eye 12, complete Overall roadway excavation project; under t...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com