Construction method for progressive excavation of plain river-adjacent reservoir basin under mucky soil condition
A technology of silt soil and construction method, applied in excavation, infrastructure engineering, waterway system and other directions, can solve the problems of difficult construction, complicated operation and high cost, and achieve the effect of solving the long construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0036] A construction method for progressive excavation of a river basin in a plain under the condition of silty soil, the method comprises the following steps:
[0037] Step 1, drive a circle of continuous stirring piles 2 along the surrounding dam toe in the reservoir basin to act as a water-stop curtain;
[0038] Step 2: Divide the entire reservoir basin into several large areas, so that each large area can be adjacent to the main road 4 in the reservoir basin area, and excavate the main drainage ditch 3 on both sides of the main road 4 in the reservoir basin area;
[0039] Step 3, use the surface layer dregs of the reservoir basin area to lay the temporary construction road 5, and compact the road surface. At the same time, the secondary drainage ditch 6 is excavated outside the temporary construction road 5. The temporary construction road 5 must pass through all large areas and form a closed loop. The temporary construction road 5 is laid out from the middle of the reser...
Embodiment 2
[0044] Based on Example 1, Example 2 lists a number of new technical features, and Example 1 can be selected or combined with them to form a number of new and different technical solutions.
[0045] Further, in the above-mentioned construction method for progressive excavation of a river basin in a plain under the condition of silty soil, the step 6 further includes:
[0046] Step 601, excavate in strips 7 in the area, and reserve temporary construction roads 5 during the excavation process;
[0047] Step 602, after the excavation of the strip 7 in the area is completed, the excavation of the temporary construction road 5 in the strip 7 is carried out.
[0048] Optionally, in the above-mentioned construction method for progressive excavation of a river basin in a plain under silty soil conditions, there are two intersecting trunk roads 4 in the reservoir basin area, and the trunk road 4 in the reservoir basin area divides the entire reservoir basin into four. large area.
[...
Embodiment 3
[0058] A construction method for progressive excavation of a river basin in a plain under the condition of silty soil, comprising the following steps:
[0059] Step 1, drive a circle of continuous stirring piles 2 in a circle along the surrounding dam toe in the reservoir basin of River 1 to act as a water-stop curtain;
[0060] Step 2, take the two intersecting main roads 4 as dividing lines, divide the entire reservoir into four large areas A, B, C and D, and excavate the main drainage ditch 3 on both sides of the main road 4 in the reservoir basin area;
[0061] Step 3, using the surface layer slag in the reservoir basin area, laying the temporary construction road 5, compacting the road surface, and excavating the secondary drainage ditch 6 outside the temporary construction road 5;
[0062] Step 4, the area between the adjacent temporary construction roads 5 is a small area, and each small area is divided into many strips 7 with a width of 60m. The strip excavation began...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com