A breeding method and original ecological technology, applied in fish farming, application, climate change adaptation, etc., can solve the problems of inability to obtain periodic dry dew, weakened adaptability of oysters, and decreased survival rate of breeding, so as to improve the environment of the breeding site , Improving immunity and promoting healthy growth
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0022] A kind of oyster off-shore original ecological culture method, comprises the following steps:
[0023] Fixed bent frame setting: Pile at a certain distance. Before piling, remove large rocks, miscellaneous algae and harmful organisms on the seabed, and level the bottom. The piles are made of wood or steel pipes wrapped in PVC pipes. The specific length of the piles depends on The actual depth of the sea water is designed, and the lines of the piles are arranged vertically and horizontally. The vertical and horizontal intervals of the piles are 2 meters and 3 meters respectively, and the horizontal bars are fixed on the piles so that the piles are fixed to each other. When the height difference between the sea surface is 1.5 meters, the horizontal bar is made of wood, bamboo or steel structure, and pedestrian passages and work rooms are set up on the horizontal bar, which is convenient for walking, breeding operation and care on it. Fix the bamboo poles in parallel on th...
Embodiment 2
[0029] A kind of oyster off-shore original ecological culture method, comprises the following steps:
[0030] Fixed bent frame setting: Pile at a certain distance. Before piling, remove large rocks, miscellaneous algae and harmful organisms on the seabed, and level the bottom. The piles are made of wood or steel pipes wrapped in PVC pipes. The specific length of the piles depends on The actual depth of the sea water is designed, and the lines of the piles are arranged vertically and horizontally. The vertical and horizontal intervals of the piles are 2 meters and 3 meters respectively, and the horizontal bars are fixed on the piles so that the piles are fixed to each other. When the height difference between the sea surface is 1.5 meters, the horizontal bar is made of wood, bamboo or steel structure, and pedestrian passages and work rooms are set up on the horizontal bar, which is convenient for walking, breeding operation and care on it. Fix the bamboo poles in parallel on th...
Embodiment 3
[0036] A kind of oyster off-shore original ecological culture method, comprises the following steps:
[0037] Fixed bent frame setting: Pile at a certain distance. Before piling, remove large rocks, miscellaneous algae and harmful organisms on the seabed, and level the bottom. The piles are made of wood or steel pipes wrapped in PVC pipes. The specific length of the piles depends on The actual depth of the sea water is designed, and the lines of the piles are arranged vertically and horizontally. The vertical and horizontal intervals of the piles are 2 meters and 3 meters respectively, and the horizontal bars are fixed on the piles so that the piles are fixed to each other. When the height difference between the sea surface is 1.5 meters, the horizontal bar is made of wood, bamboo or steel structure, and pedestrian passages and work rooms are set up on the horizontal bar, which is convenient for walking, breeding operation and care on it. Fix the bamboo poles in parallel on th...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com