Construction method of circuitous pilot tunnel for preventing and treating water inrush of tunnel
A construction method and technology of inrush water, applied in tunnels, tunnel lining, drainage, etc., can solve problems such as prolonging construction period, surrounding rock disturbance, and increasing investment costs.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0041] see Figure 1-4 , this embodiment provides a construction method for preventing tunnel water inrush and roundabout guide pit. The roundabout guide pit adopts a trackless transport single lane V-level composite section, the reserved amount of deformation is 15cm, and I-shaped steel is used to strengthen the support. It is characterized in that: Also includes the following steps:
[0042] S1: Pre-construction treatment;
[0043] S2: excavation by step method;
[0044] S3: support construction;
[0045] S4: advance support;
[0046] S5: shotcrete;
[0047] S6: Construction of weep holes on the side wall of the roundabout pilot pit.
[0048] In the construction method of the circuitous diversion pit for preventing tunnel water inrush provided by this embodiment, in the step S1, the pre-construction treatment includes:
[0049] Strengthen the support of the main hole arch frame at the junction of the main hole and the roundabout pilot pit top, and add locking feet. The...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com