A construction technique and clean workshop technology, applied in the field of high-clean workshop processing, can solve the problems of low air cleanliness in clean rooms, affecting the use of workshops, and high dust generation, so as to avoid waste of resources, avoid waste of time, and improve effectiveness Effect

Inactive Publication Date: 2019-12-13
CHONGQING CONSTR RESIDENTIAL ENG +2
View PDF3 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] In recent years, with the rapid development of the country's economy and technology, the requirements for environmental cleanliness have become higher and higher for medical treatment, pharmaceuticals, microelectronics processing, clean processing workshops, and high-end technology research and development. Higher and more professional requirements are required, and there are many professional pipelines in the high-cleanness workshop and the layout is very concentrated. There are also various process equipment and production equipment. Compared with other industrial workshops, there are special process requirements. If the pipeline construction Improper use will cause the problems of low air cleanliness and high dust generation in the clean room, which will affect the use of the factory building and further affect the production

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0017] In order to make the technical means, creative features, goals and functions achieved by the present invention clearer and easier to understand, the present invention will be further elaborated below in conjunction with specific embodiments:

[0018] A pipeline construction process for a clean workshop, comprising the following construction steps:

[0019] S1. Prefabrication and installation of clean outdoor pipeline supports and hangers: set up supports and hangers at the beginning of the air duct and the connection with the same equipment, and support the vertical outer pipelines on each floor with supports and hangers. When the floor height is ≥ 5m, two supports and hangers should be installed The opening of the frame and the hanging bracket is matched with a bench drill and a hand drill;

[0020] S2. Manufacture and hoisting of clean outdoor pipelines: the main pipes of the clean outdoor pipelines are made of galvanized steel pipes, the branch pipes are made of stai...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction process of a clean workshop pipeline. The construction process comprises the following construction steps: 1, prefabricating and installing an external pipelinesupport hanger of a clean room; 2, manufacturing and hoisting an external pipeline of the clean room; 3, welding the pipeline; 4, carrying out argon arc welding; 5, carrying out glue bonding; 6, installing an air pipe of the clean room; 7, testing the pipeline; and 8, preserving heat of the pipeline. Sealing welding, argon arc welding and glue bonding sealing connection are respectively carried out on galvanized steel pipes, stainless steel pipes and PVC pipes in the external pipeline of the clean room, the air pipe of the clean room is installed by adopting cleaning work clothes, gloves and working shoes, and the seal is completed after being connected, so that the built clean room completely meets the requirement of precision machining on a clean room, the sustainability and the high quality of product production are guaranteed, the production effectiveness is improved, unnecessary waste on time and materials are avoided, and the time cost and the economic cost are saved.

Description

technical field [0001] The invention relates to the technical field of high-cleanness factory building processing, in particular to a clean factory building pipeline construction process. Background technique [0002] In recent years, with the rapid development of the country's economy and technology, the requirements for environmental cleanliness have become higher and higher for medical treatment, pharmaceuticals, microelectronics processing, clean processing workshops, and high-end technology research and development. Higher and more professional requirements are required, and there are many professional pipelines in the high-cleanness workshop and the layout is very concentrated. There are also various process equipment and production equipment. Compared with other industrial workshops, there are special process requirements. If the pipeline construction Improper use will cause problems such as low air cleanliness and high dust generation in the clean room, which will af...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): F24F13/02
CPCF24F13/0245
Inventor 陈怡宏舒唯华建民李晓倩黄乐鹏刘懿
Owner CHONGQING CONSTR RESIDENTIAL ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products