A technology of comprehensive control and control system, which is applied in mine/tunnel ventilation, pump control, wind engine, etc. It can solve the problems of large power consumption and insufficient utilization of tunnel fan wind energy, so as to reduce power consumption and realize The effect of repeated use and good application value
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0035] The length of a highway tunnel is 1km, the design driving speed is 80km / h, and the ventilation method is designed as jet mechanical ventilation. see Figure 1 to Figure 4 , an example is given.
[0036] Step 1: Calculate the number of generating units according to the length of the tunnel and the installation distance, and prepare the required 200 sets of road vibration generating units in advance. Conductors lead out for standby, forming a road power generation system 5;
[0037] Step 2: After the tunnel construction is completed, install the jet fan 2. The required number and installation distance of the jet fan 2 are determined according to the length of the tunnel and the traffic flow. ready to use;
[0038] Step: 3: Determine the quantity of required wind generators 3 according to the length of the tunnel 1 and the number of jet fans, install the wind generators 3 symmetrically at the left and right side walls of the tunnel 1, and arrange the leads for standby; ...
Embodiment 2
[0044] The length of a highway tunnel is 6km, and the design driving speed is 80km / h. The ventilation method is a vertical shaft equipped with jet-type longitudinal ventilation, and a vertical shaft is set in the middle of the tunnel. see figure 1 , figure 2 and Figure 5 , giving another example.
[0045] Step 1: Calculate the number of generating units according to the length of the tunnel and the installation distance, and prepare the required 1200 sets of road vibration generating units in advance. Conductors lead out for standby, forming a road power generation system 5;
[0046] Step 2: After the tunnel construction is completed, install the jet fans 2. The required number and installation spacing of the jet fans 2 are determined according to the length of the tunnel, the traffic volume and the height of the shaft. The jet fans 2 are installed in groups of two on the tunnel vault and the shaft. , the power line and control line are ready for use;
[0047] Step: 3: ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com