Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Railway nonstandard beam erection construction method

A technology for standard beams and railways, applied in bridge construction, erection/assembly of bridges, bridges, etc., can solve the problems of high cost of foundation treatment of strip foundations or pile foundations, and large amount of steel, achieving high erection efficiency and saving production costs. , the effect of simple operation

Inactive Publication Date: 2017-03-08
CHINA RAILWAY SIXTH GRP CO LTD
View PDF5 Cites 7 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The original design adopts the cast-in-place plan of the bracket, but the cast-in-place construction of the bracket is used, the box girder model, turnover materials and high; and the pier body is high, and the steel pipe column bracket system requires a large amount of temporary columns and section steel, plus foundation treatment Strip or pile foundations are more expensive

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Railway nonstandard beam erection construction method
  • Railway nonstandard beam erection construction method
  • Railway nonstandard beam erection construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0035] The present invention will be further described in detail below with reference to the drawings and an embodiment.

[0036] Such as figure 1 with figure 2 As shown, in the process of installing the lower guide beam support in the present invention, according to the different hole spans of the non-standard beam, the installation position of the front support leg should be recalculated at the front end of the lower guide beam, and the front support leg should be installed; Re-drill holes on the bottom plate of the lower guide beam, and weld the supporting stiffener plate inside the guide beam box.

[0037] A new construction bid section in front of a railway passenger dedicated line with a total length of 40.308 kilometers and a total of 1074 hole box girder erected. Among them, in order not to encroach on small rivers, ditches, and cross-country roads, 3-hole non-standard box girder is used for hole span adjustment.

[0038]

[0039] This construction method realizes the erect...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a railway nonstandard beam erection construction method and belongs to the technical field of erection methods of nonstandard beams. The railway nonstandard beam erection construction method comprises the steps of 1) lifting beams to a beam truck from a beam site; 2) transporting box beams; 3) feeding the beams; 4) lowering the beams; 5) returning the beam truck, and filling with support mortar; 6) passing a bridge machine through a hole. Before the step 1), a step of mounting lower guide beam legs is also provided; in the process of mounting the lower guide beam legs, mounting positions for calibrating front legs are recalculated at the front ends of lower guide beams according to different spans of non-standard beams, and the front legs are mounted. The railway nonstandard beam erection construction method provides high erection efficiency, and has greatly saved production cost.

Description

Technical field [0001] The invention relates to the technical field of erection methods of non-standard beams. Background technique [0002] At present, in the erection of railway bridges, the spans of standard box girder are basically 20m, 24m and 32m. The erection techniques and methods are relatively mature. However, in engineering construction, some bidding sections are often encountered. Standard box girder. [0003] The tender section in front of a railway passenger dedicated line station has a total length of 40.308 kilometers and a total of 1074 hole box beams. In order not to encroach on small rivers, ditches, and cross-country roads, 3 hole non-standard box girder is used for hole span adjustment. [0004] The original design adopts the support cast-in-place scheme, but uses the support cast-in-place construction, box girder model, turnover materials and higher; and the pier body is higher, the use of steel pipe column support system requires a large amount of temporary c...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00
CPCE01D21/00
Inventor 高振华陈永刚张亚松丁鹏程王彬冯霖国永智谢月明王弘道刘锦翼王自超
Owner CHINA RAILWAY SIXTH GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products