Wind field road construction method
A technology for road construction and wind field, which is applied in the direction of roads, roads, side ditches/curbs, etc., and can solve problems such as poor site stability, fractures, landslides, and collapses
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0028] A method for road construction in a wind field, including road construction, circular pipe culvert construction and retaining wall construction, the specific steps are:
[0029] (1), road construction:
[0030] a. First, measure the positioning and setting out, and control the distance between the measurement and control piles at 20m each. After the control piles are set up, drive a φ25 steel reinforcement pile into one end of the construction section, fix one end of the tensioner on the reinforcement pile, and fix the steel wire rope at the other end. Then pull the steel wire rope to make the tensile force of the tensioner reach more than 10N. The length of the steel wire rope is preferably 100-130m for each construction section. Just tie the wires. When the steel wire rope sags too much, add a support between every two test piles to prevent the steel wire rope from sinking due to too long pile distance. ;
[0031] b. Stockpile and pave the road into the wind field a...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com