A construction method and technology of hard soil, applied in sheet pile wall, foundation structure engineering, construction, etc., can solve the problems of pile core soil rising, difficulty in sinking mold, etc., so as to reduce soil extrusion pressure, easy to sink piles, and easy to realize Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0027] Such as figure 1 As shown in (a), before the pile driver is in place, soil is taken from the center of the pile to form a reserved cavity 13 . Reserve cavity 13 sectional areas (as figure 2 (a) The area of the small circle) and the area between the inner and outer tubes of the pile (such as figure 2 (a) The area of the circle formed by the two dotted lines) is equal, and the depth is the same as the maximum depth of sinking of the inner pipe 1 of the pile form, at this time figure 1 The section diagrams along the lines C-C and D-D are as follows figure 2 As shown in (a), the dotted line indicates the position of the pile formwork. At this time, the pile foundation is not in place yet, and the small circle with the solid line in the center indicates the outer contour of the reserved cavity 13 . Such as figure 1 As shown in (b), before the pile foundation is in place, the pile formwork is assembled and the spud cans are closed. The switch control that clamp 11...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com