Automatic gain scheduling method for wind power plants distributed as priority level according to blower involvement

A technology of fan output and automatic scheduling, which is applied to wind power generation, single-network parallel feeding arrangement, etc., to reduce the failure rate of fans and increase the power generation effect

Inactive Publication Date: 2014-10-29
STATE GRID CORP OF CHINA +3
View PDF4 Cites 9 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The traditional wind farm active power control methods such as proportional and margin-based methods no longer meet these new requirements, and a new active power control method for wind farms needs to be studied to meet these requirements.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0019] The automatic dispatching method of the present invention is introduced below with a specific embodiment of the automatic dispatching of the active power of the wind farm that considers the output of wind turbines according to the priority level distribution of a certain wind farm:

[0020] The total installed capacity of the wind farm in this embodiment is 99.5MW, including 33 1.5MW wind turbines of United Power in the first phase and 25 2.0MW wind turbines in Chongqing Haizhuang in the second phase. The specific scheduling method is as follows:

[0021] 1) According to the power generation capacity of the wind turbines, the wind turbines are divided into two types: ordinary wind turbines and benchmark wind turbines for active power scheduling, and priority is given to ensuring that the benchmark wind turbines are fully powered;

[0022] 2) Divide benchmark wind turbines from low to high into grades 1, 2, and 3; those with higher grades are given priority to full power...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to an automatic gain scheduling method for wind power plants distributed as the priority level according to blower involvement and belongs to the technical field of energy management system of power systems. The automatic gain scheduling method includes classifying blowers into common blowers and marker blowers according to power generation capacity of the blowers and scheduling the same in a gain manner, and giving the priority to involving all the marker blowers to generate power; classifying the marker blowers from low to high by a first level, a second level and a third level; giving the priority to involving all the blowers at high level to generate power; performing no power ration control at the third level which is the highest level; receiving gained control targets of dispatching, wherein when the gained control targets are larger than or equal to loading capacity, the dispatching command is that all the blowers generate power freely; when the gained control targets are smaller than the loading capacity, power ration control on blower involvement is performed; when on-grid gain is smaller than the gained control targets *95%, guaranteeing complete involvement of the marker blowers at the first level, the second level and the third level according to the sequence, and then adjusting the common blowers. The automatic gain scheduling method is simple and easy to realize, power generation capacity of the wind power plants can be increased, and fault rate of the blowers can be decreased.

Description

technical field [0001] The invention belongs to the technical field of electric power system energy management system (EMS), and in particular relates to a method for automatically dispatching active power of a wind farm considering the distribution of fan output according to priority levels. Background technique [0002] In recent years, many large-scale wind power bases across the country have been built and put into operation, which has changed the original power supply structure. The impact of wind power on the power grid has gradually increased, from the reactive power and voltage of the local power grid to the peak regulation and frequency regulation of the large power grid. influences. The "Technical Regulations for Connecting Wind Farms to the Power Grid" issued by the State Grid Corporation of China pointed out: "Wind farms should have the ability to regulate active power and be able to control their active power output according to the instructions of the grid disp...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): H02J3/48
CPCY02E10/76
Inventor 孙勇汤磊郑太一王彬蔡宏毅吴文传范国英张伯明杨国新孙宏斌曹政王岗红
Owner STATE GRID CORP OF CHINA
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products