Road passage underground project construction method
A technology for underground engineering and road traffic, applied in water conservancy projects, infrastructure engineering, artificial islands, etc., can solve the problems of low excavation depth and low excavation speed, and achieve the effect of low engineering investment, low construction difficulty and safe construction
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0048] Taking the construction of underground garages in places with narrow roads and large traffic volumes, such as railway stations, as an example, the first construction method is adopted:
[0049] (1) Divide the construction ground into three sections, namely, section C in the middle and sections A and B on both sides
[0050] (2) Close Section C, set up enclosure structures and road fences around, and divert traffic. Before excavating the surface soil, carry out two rows of pile foundation construction and steel lattice column construction, and excavate the surface soil for Section C construction. Make the roof 1 of section C; the roof 1 of section C is connected with two rows of steel lattice columns to form a reinforced concrete bridge;
[0051] (3) Restore the pipeline, backfill the earthwork of section C, restore traffic, construct steel sheet piles or bored piles for section A, and make surrounding beams to form the enclosure structure of the foundation pit, and then...
Embodiment 2
[0057] Taking the construction in places with wide roads and small traffic flow as an example, the second scheme is used for construction:
[0058] (1) Divide the construction ground into three sections, namely, section C in the middle and sections A and B on both sides
[0059] (2) Close Section C, set up enclosure structures and road fences around, and divert traffic. Before excavating the surface soil, carry out two rows of pile foundation construction and steel lattice column construction, and excavate the surface soil for Section C construction. Make the roof 1 of section C; the roof 1 of section C is connected with two rows of steel lattice columns to form a reinforced concrete bridge;
[0060] (3) Restore the pipeline, backfill the earthwork of section C, restore traffic, construct sections A and B at the same time, construct steel sheet piles or bored piles, and make surrounding beams to form the enclosure structure of the foundation pit, and then pile foundation constru...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com