Steel strand prestress base structure of wind driven generator and construction method thereof
A technology for wind turbines and infrastructure, applied in infrastructure engineering, construction, etc., can solve the problems of excessive consumption of materials, reduced impact resistance, insufficient tensile force, etc. The effect of pull-out resistance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0055] Embodiment 1: The construction method of the basic structure of the present invention with a 1.5MW wind power generator installed (rock formation geological conditions).
[0056] (1) Dig a foundation pit with a diameter of 10m and a depth of 1.6m on the surface.
[0057] (2) At the bottom of the foundation pit along the circumference, two adjacent equidistant, drill straight holes 5 with a diameter of 150mm, a depth of 10m, and a number of 30. The distance between the center of the straight holes 5 and the center of the foundation pit is 4.5m .
[0058] (3) Use the reaming drill bit equipment to ream the bottom of the straight hole 5, the diameter of the reaming hole 2 is 250mm, and the height is 400mm.
[0059] (4) Drill a 200mm deep elongated hole 16 at the bottom of the reamed hole 2, and put a bamboo shoot 15 in the elongated hole 16, with a diameter of 140mm and a height of 300mm.
[0060] (5) Put steel strands 3 and 7 with metal embossing 1 at the bo...
Embodiment 2
[0068] Embodiment 2: The construction method of the basic structure of the present invention with a 2MW wind power generator installed (rock formation geological conditions).
[0069] (1) Dig a foundation pit with a diameter of 10m and a depth of 1.6m on the surface.
[0070] (2) At the bottom of the foundation pit along the circumference, two adjacent equidistant, drill straight holes 5 with a diameter of 150mm, a depth of 10m, and a number of 28. The distance between the center of the straight holes 5 and the center of the foundation pit is 4.5m .
[0071] (3) Use the reaming drill bit equipment to ream the bottom of the straight hole 5, the diameter of the reaming hole 2 is 250mm, and the height is 400mm.
[0072] (4) Drill a 200mm deep elongated hole 16 at the bottom of the reamed hole 2, and put a bamboo shoot 15 in the elongated hole 16, with a diameter of 140mm and a height of 300mm.
[0073] (5) Put 3 or 6 steel strands that have been tightened with posit...
Embodiment 3
[0081] Embodiment 3: The construction method of the basic structure of the present invention with a 2MW wind power generator installed (rock formation geological conditions).
[0082] (1) Dig a foundation pit with a diameter of 10m and a depth of 1.6m on the surface.
[0083] (2) At the bottom of the foundation pit along the circumference, two adjacent equidistant, drill straight holes 5 with a diameter of 150mm, a depth of 10m, and a number of 30. The distance between the center of the straight holes 5 and the center of the foundation pit is 4.5m .
[0084] (3) Use the reaming drill bit equipment to ream the bottom of the straight hole 5, the diameter of the reaming hole 2 is 250mm, and the height is 400mm.
[0085] (4) Drill a 200mm deep elongated hole 16 at the bottom of the reamed hole 2, and put a bamboo shoot 15 in the elongated hole 16, with a diameter of 140mm and a height of 300mm.
[0086] (5) Put steel strands 3 and 6 with metal embossing 1 at the botto...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com