Non-forecast flood regulation method for cascade hydropower station based on water level flow
A flood dispatching, non-forecasting technology, applied in hydropower stations, traditional hydropower energy, hydropower, etc., can solve the problems of difficult reservoir charging, ineffective flood resource utilization, etc., to prevent flooding accidents, guarantee safe effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0044] Embodiment of the present invention: the unforecasted flood dispatching method of the cascade hydropower station based on water level and flow, such as figure 1 shown, including the following steps:
[0045] S1, determine the storage capacity ΔV from the current water level to the set high water level (or given final water level). If the storage water level is the flood limit water level before the flood, the set high water level is the flood control high water level. At this time, ΔV It is exactly the flood control storage capacity of the reservoir;
[0046] S2, always maintain the discharge at the full flow of the unit until half of the storage capacity is stored;
[0047] S3, the inbound flow Q(t) facing the time period is the peak flow Q facing the flood 峰 , the following method is used to calculate the inbound flow Q(t) in the facing period: Q(t)=(V(t+1)-V(t)) / Δt+q(t), where V(t+1) is t The storage capacity of the reservoir at the end of the period, V(t) is the ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com