Problems solved by technology

In existing karst-developed areas, bridge bored piles are often drilled in a hole-deviation phenomenon. The existing deviation-rectification technical scheme is: throwing and filling high-strength flakes, and then using a percussion drill to correct the deviation; after measurement, the inclination of the drilled hole cannot If the requirements are met, high-strength flakes are thrown and filled, and the impact drill is repeatedly impacted to correct the deviation
The shortcoming of prior art scheme: (1) to the partial hole that rock stratum strength is not big in borehole, throw and fill rubble, can rectify deviation with percussion drill repeated impact, but progress is slow, needs to use a large amount of high-strength rubble, and cost is high; ( 2) For the partial hole with high rock formation strength in the drilled hole, throwing and filling the chip, and repeatedly impacting the impact drill with the percussion drill, the correction effect is not obvious, the progress cannot be guaranteed, the quality cannot be guaranteed, and it is easy to cause labor disputes

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for correcting inclined hole formed by high strength stratum bridge drilling pile in karst growing area
  • Method for correcting inclined hole formed by high strength stratum bridge drilling pile in karst growing area

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0022] Such as figure 1 As shown, a method for rectifying the deviation of the inclined hole of the high-strength rock formation bridge bored pile in the karst developed area is characterized in that the method is composed of the following steps:

[0023] (1) Verify the location of the inclined rock to determine the exact position and direction of the inclined rock;

[0024] (2) Use a small geological drilling rig to drill a small hole on the top of the inclined rock next to the inclined hole;

[0025] (3) Waterproof explosives are sent into the underwater small hole;

[0026] (4) Carry out underwater controlled blasting to break or loosen rock formations;

[0027] (5) Then use the percussion drill to impact the broken or loose rock formation, so as to correct the deviation of the drilling hole and quickly form a hole.

[0028] The position of the small hole drilled by a small geological drilling rig is 200-300mm from the top of the inclined rock next to the inclined hole, ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a method for correcting an inclined hole formed by a high strength bridge drilling pile in a karst growing area. The invention is characterized in that the method comprises the following steps: (1) verifying the position in which a plagioclase is located, and determining the accurate position and direction of the plagioclase; (2) drilling small holes on the top surface of the plagioclase beside the inclined hole by adopting a minitype geological drilling machine; (3) feeding water-proof explosive into the underground small hole; (4) carrying out underground controlled blasting to crush or loosen the stratum; and (5) carrying out percussion on the crushed or loosened stratum by a percussion drill, thus the aims of correcting the deflection of a drill hole and rapidly forming a hole are achieved. The small hole drilled by adopting the minitype geological drilling machine is 200-300mm away from the top surface of the plagioclase beside the inclined hole, the diameter of the small hole is 85-95mm, and the drilling depth is 2-8-3.5m in the plagioclase. The construction method applied in the invention can be popularized in the railway, road and municipal bridge projects, a continuous beam for crossing is not required by a complex drilling pile in the karst growing area, thus saving the investment; and the construction progress can be sped up, and the application prospect is wide.

Description

technical field [0001] The invention relates to a method for rectifying the deviation of inclined holes of bridge bored piles in high-strength rock formations in karst-developed areas. Background technique [0002] According to the requirements of the national standard, the inclination of the drilled holes of the bridge bored piles must be less than or equal to 1% of the hole depth, so as to ensure the bearing capacity requirements of the bored piles. In existing karst-developed areas, bridge bored piles are often drilled with partial hole phenomenon. The existing technical solution for correcting the deviation is: throwing and filling high-strength flakes, and then using a percussion drill to correct the deviation; after measurement, the inclination of the drilled hole cannot If the requirements are met, high-strength flakes are thrown and filled, and the impact drill is used to repeatedly impact and correct the deviation. The shortcoming of prior art scheme: (1) to the pa...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/34E02D5/38E21B7/10
Inventor 刘汉银刘飞
Owner CHINA RAILWAY 22ND BUREAU GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products