Upper chord bracing for high-altitude assembly of pipe truss and construction method of upper chord bracing

A construction method and technology of pipe trusses, applied in the preparation of pillars and building components on site, construction, etc., can solve problems such as complex operations and impact on quality, and achieve the effects of simplifying the operation process, improving turnover efficiency, and ensuring assembly accuracy

Pending Publication Date: 2021-08-06
SCEGC MECHANIZED CONSTR GRP COMPANY
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The purpose of the present invention is to solve the above-mentioned problems in the prior art that the steel pipe truss is assembled at high altitude and the construction is complicated and affects the quality, and to provide a steel pipe truss high-altitude assembled upper chord support and its construction method, which simplifies the operation process and ensures the assembly accuracy

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Upper chord bracing for high-altitude assembly of pipe truss and construction method of upper chord bracing
  • Upper chord bracing for high-altitude assembly of pipe truss and construction method of upper chord bracing
  • Upper chord bracing for high-altitude assembly of pipe truss and construction method of upper chord bracing

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0028] The present invention will be described in further detail below in conjunction with the accompanying drawings.

[0029] see figure 1 , the present invention proposes a pipe truss high-altitude assembled upper chord support, including a column support body, the column support body is assembled from a lower column support part 1 and an upper column support part 2, and the assembly surface is a slope; the top of the upper column support part 2 A U-shaped groove part 3 for fixing the pipe truss 4 is provided. see figure 2 , image 3 , the upper column support part 2 includes an upper column 9 and an upper column upper supporting plate 10 arranged on the upper surface of the upper column 9, the upper supporting plate 10 of the upper column is provided with a U-shaped card groove part 3 for fixing the pipe truss 4, and the lower column The support part 1 comprises a lower column 6, the bottom surface of the lower column 6 is horizontally provided with the lower supporting...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses an upper chord bracing for high-altitude assembly of a pipe truss and a construction method of the upper chord bracing. The upper chord bracing comprises a stand column bracing body, the stand column bracing body is formed by assembling a lower stand column bracing part and an upper stand column bracing part, and the assembling face is an inclined face; the upper stand column bracing part comprises an upper stand column and an upper stand column upper supporting plate arranged on the top face of the upper stand column, the upper stand column upper supporting plate is provided with a U-shaped clamping groove part used for fixing the pipe truss, the U-shaped clamping groove part is composed of a first T-shaped structural plate and a second T-shaped structural plate, the first T-shaped structural plate and the second T-shaped structural plate each comprise a vertical plate and a vertical plate supporting plate, and the pipe truss is fixed between the vertical plates of the two T-shaped structural plates; and the vertical plate supporting plates are connected with the upper stand column upper supporting plate through bolts, strip-shaped holes are formed in the upper stand column upper supporting plate, the bolts can pass through the strip-shaped holes, the vertical plate distance between the two T-shaped structural plates can be adjusted according to the diameter of the pipe truss, and the forming direction of the strip-shaped holes is the moving direction of the two T-shaped structural plates. The upper chord bracing simplifies the operation process and can guarantee the assembly precision.

Description

technical field [0001] The invention belongs to the field of building construction, and in particular relates to a high-altitude assembled upper chord support of a pipe truss and a construction method thereof. Background technique [0002] The large-span three-dimensional steel pipe truss structure of the roof of various venues usually adopts the construction method of high-altitude loose assembly due to the characteristics of high building density, small spacing between building units, and no large assembly site around the venue. During the sliding process of the steel pipe truss that adopts the high-altitude loose construction method, there is a conflict between the chord and the upper chord support vertical rod route, and the upper chord support requires frequent overall installation and disassembly, and the process is complicated. During the removal process of the upper chord support, the steel pipe truss needs to be lifted and unloaded as a whole, which is likely to cau...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E04G21/16E04G25/02E04G21/14
CPCE04G21/14E04G21/16E04G25/02
Inventor 胡生元李亮王晓亭王昆王龙王明岗樊晨虎
Owner SCEGC MECHANIZED CONSTR GRP COMPANY
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products